This record is an infrastructure/permit case, not a standalone compute facility: an Adams County conditional use submittal for a transmission line to serve a new data center campus at 24600 E Smith Rd. The served campus is not definitively identified; it may correspond to the Vantage CO21, NTT DN1, or Microsoft Aurora sites in the same corridor. Retained with possible_duplicate_of pointers rather than merged.
Key data: RCU2024-00008
Claim classification: Not yet assigned
Status date: 2026-09-14