Compute Equity Atlas
← National map
Source-backed project record · OH

Meta Bowling Green Data Center

This record consolidates 1 research observations while retaining source distinctions, location precision and unresolved fields.

proposed_or_reviewproject status
SOURCE_BACKEDbest evidence tier
1linked evidence rows
Project facts

Location and operating record

Operator / developerMeta
JurisdictionMiddleton Township, Wood County, OH
AddressNot published
Location precisionlocality
CoordinatesNot published; no coordinate inferred
CapacityNot established
AliasesNone retained
Evidence coverage

What has been researched

Project profile0 rows
Intent / permits0 rows
Civic / infrastructure0 rows
REVIEWED PROJECT UPDATES

Meta Bowling Green Data Center: reviewed project updates

Source observation

Meta announced its Bowling Green campus in Middleton Township, Wood County, on April 9, 2025.

Key data: The announcement describes a planned 715,000-square-foot campus and names Toledo Edison as the electric-service planning partner.

Claim classification: Attributed source observation · Verification: Listed fields reviewed; not a site inspection · Retrieved: 2026-10-03

Status date: 2025-04-09

Limitation: The dated announcement supports identity and locality, not a current operating status or completed capacity.

Open source 1 →

Sources

Evidence and provenance

  • datacenters.atmeta.com ↗ · Retrieved 2026-10-03 · SOURCE BACKED
    Limitation: The dated announcement supports identity and locality, not a current operating status or completed capacity.

Open OH state research →

Meta Bowling Green Data Center Data Center Project | Middleton Township, Wood County | Compute Equity Atlas