Source observation
Microsoft's July 2026 update reports site preparation at its Hebron datacenter, including grading, fencing, stormwater ponds and erosion controls.
Key data: The March update describes a temporary construction entrance off Canyon Road and distinguishes early site work from subsequent vertical construction.
Claim classification: Attributed source observation · Verification: Listed fields reviewed; not a site inspection · Retrieved: 2026-10-03
Status date: 2026-07
Limitation: Construction here describes site work. Construction completion and datacenter operation are different milestones.