Compute Equity Atlas
← National map
Source-backed project record · OH

Microsoft Hebron Datacenter

This record consolidates 1 research observations while retaining source distinctions, location precision and unresolved fields.

under_constructionproject status
SOURCE_BACKEDbest evidence tier
1linked evidence rows
Project facts

Location and operating record

Operator / developerMicrosoft
JurisdictionHebron, OH
AddressNot published
Location precisionlocality
CoordinatesNot published; no coordinate inferred
CapacityNot established
AliasesNone retained
Evidence coverage

What has been researched

Project profile0 rows
Intent / permits0 rows
Civic / infrastructure0 rows
REVIEWED PROJECT UPDATES

Microsoft Hebron Datacenter: reviewed project updates

Source observation

Microsoft's July 2026 update reports site preparation at its Hebron datacenter, including grading, fencing, stormwater ponds and erosion controls.

Key data: The March update describes a temporary construction entrance off Canyon Road and distinguishes early site work from subsequent vertical construction.

Claim classification: Attributed source observation · Verification: Listed fields reviewed; not a site inspection · Retrieved: 2026-10-03

Status date: 2026-07

Limitation: Construction here describes site work. Construction completion and datacenter operation are different milestones.

Open source 1 →

Sources

Evidence and provenance

  • local.microsoft.com ↗ · Retrieved 2026-10-03 · SOURCE BACKED
    Limitation: Construction here describes site work. Construction completion and datacenter operation are different milestones.