Source-backed project record · NE

ArchGreen Infrastructure Grand Island Project 1

This record consolidates 7 research observations while retaining source distinctions, location precision and unresolved fields.

approved_or_permittedproject status
SOURCE_BACKEDbest evidence tier
7linked evidence rows
Project facts

Location and operating record

Operator / developerArchGreen Infrastructure
JurisdictionGrand Island, NE
AddressSite on 60th Road, about a quarter mile south of Capital Avenue and roughly two miles north of the Old Potash Highway / 60th Road intersection, northwest of Grand Island
Location precisionparcel or bounded site
CoordinatesNot published; no coordinate inferred
CapacityNot established
AliasesArchGreen Infrastructure Grand Island Project 1 · ArchGreen Grand Island
Evidence coverage

What has been researched

Project profile0 rows
Intent / permits0 rows
Civic / infrastructure0 rows
SOURCE RECORD

ArchGreen Infrastructure Grand Island Project 1: source record

permitted

Design described as 14 compute containers plus two additional units, 12.5 MW, on land leased from Southern Public Power District. No fetched source confirms whether the facility was actually built and energized, so status remains 'permitted' rather than operational.

Key data: Southern Public Power District (site leased from Southern Public Power District) | Southwest Power Pool (SPP)

Claim classification: Not yet assigned

Status date: 2026-09

Open source 1

OWNERSHIP AND PROFILE

ArchGreen Infrastructure Grand Island Project 1: ownership and profile

permitted

Developer: ArchGreen Infrastructure | County: Hall | Research region: Central Nebraska

Claim classification: Not yet assigned

Status date: 2026-09

Open source 1

POWER AND GRID

ArchGreen Infrastructure Grand Island Project 1: power and grid

permitted

Key data: Utility: Southern Public Power District (site leased from Southern Public Power District) | Grid area: Southwest Power Pool (SPP) | Requested load MW: 12.5

Claim classification: Not yet assigned

Status date: 2026-09

Open source 1

WATER AND COOLING

ArchGreen Infrastructure Grand Island Project 1: water and cooling

PERMITS AND JURISDICTION

ArchGreen Infrastructure Grand Island Project 1: permits and jurisdiction

permitted

Key data: Permit IDs: Hall County conditional use permit granted by resolution Jan. 31, 2023, expiring Jan. 31, 2028 | Jurisdictions: Hall County | Nebraska

Claim classification: Not yet assigned

Status date: 2026-09

Open source 1

TIMELINE

ArchGreen Infrastructure Grand Island Project 1: timeline

permitted

Hall County conditional use permit public hearing

Claim classification: Not yet assigned

Status date: 2023-01-17

Open source 1

permitted

Conditional use permit resolution adopted; permit expires Jan. 31, 2028

Claim classification: Not yet assigned

Status date: 2023-01-31

Open source 1

Sources

Evidence and provenance

Open NE state research →

ArchGreen Infrastructure Grand Island Project 1 Data Center Project | Grand Island | Compute Equity Atlas