The Hawk Eye toured the facility: roughly 7 acres with about 3 acres in use, dry cooling, produced bitcoin since September 2025. A separate 25 MW AI data center is proposed at the same site (announced, not approved) and Des Moines County adopted Resolution 2026-034, a one-year moratorium, on May 19, 2026. Jackson County's earlier moratoria were also linked to an Aurum ~2.5 MW proposal per the moratorium dataset.
Key data: Eastern Iowa Light & Power / adjacent Alliant Energy substation (as described in local reporting)
Claim classification: Not yet assigned
Status date: 2026-08