Source-backed project record · IA

Aurum Capitol Ventures Middletown Bitcoin Mine

This record consolidates 9 research observations while retaining source distinctions, location precision and unresolved fields.

operationalproject status
SOURCE_BACKEDbest evidence tier
9linked evidence rows
Project facts

Location and operating record

Operator / developerAurum Capitol Ventures
JurisdictionMiddletown, IA
AddressNot published
Location precisionlocality centroid
Coordinates40.827862, -91.262227
CapacityNot established
AliasesAurum Capitol Ventures Middletown Bitcoin Mine · Middletown site
Evidence coverage

What has been researched

Project profile0 rows
Intent / permits0 rows
Civic / infrastructure2 rows
SOURCE RECORD

Aurum Capitol Ventures Middletown Bitcoin Mine: source record

operational

The Hawk Eye toured the facility: roughly 7 acres with about 3 acres in use, dry cooling, produced bitcoin since September 2025. A separate 25 MW AI data center is proposed at the same site (announced, not approved) and Des Moines County adopted Resolution 2026-034, a one-year moratorium, on May 19, 2026. Jackson County's earlier moratoria were also linked to an Aurum ~2.5 MW proposal per the moratorium dataset.

Key data: Eastern Iowa Light & Power / adjacent Alliant Energy substation (as described in local reporting)

Claim classification: Not yet assigned

Status date: 2026-08

Open source 1

OWNERSHIP AND PROFILE

Aurum Capitol Ventures Middletown Bitcoin Mine: ownership and profile

operational

Developer: Aurum Capitol Ventures | County: Des Moines | Research region: Southeast Iowa

Claim classification: Not yet assigned

Status date: 2026-08

Open source 1

POWER AND GRID

Aurum Capitol Ventures Middletown Bitcoin Mine: power and grid

operational

Key data: Utility: Eastern Iowa Light & Power / adjacent Alliant Energy substation (as described in local reporting) | Substations: Adjacent substation next to the mine site

Claim classification: Not yet assigned

Status date: 2026-08

Open source 1

WATER AND COOLING

Aurum Capitol Ventures Middletown Bitcoin Mine: water and cooling

operational

Key data: Water demand: Operator estimates about 350,000 gallons per year if humidification were needed; reports none used to date | Cooling: Dry (air) cooling

Claim classification: Not yet assigned

Status date: 2026-08

Open source 1

PERMITS AND JURISDICTION

Aurum Capitol Ventures Middletown Bitcoin Mine: permits and jurisdiction

operational

Key data: Jurisdictions: Des Moines County | IA

Claim classification: Not yet assigned

Status date: 2026-08

Open source 1

CIVIC AND COMMUNITY

Aurum Capitol Ventures Middletown Bitcoin Mine: civic and community

operational

Reported $2.6M electricity spend in 2025 at about $0.06/kWh

Claim classification: Not yet assigned

Status date: 2026-08

Open source 1

operational

Noise concerns raised by neighbors

Claim classification: Not yet assigned

Status date: 2026-08

Open source 1

TIMELINE

Aurum Capitol Ventures Middletown Bitcoin Mine: timeline

operational

Mine began producing bitcoin

Claim classification: Not yet assigned

Status date: 2025-09

Open source 1

operational

Operator proposed a 25 MW AI data center at the site; Des Moines County adopted a one-year data center moratorium

Claim classification: Not yet assigned

Status date: 2026

Open source 1