Colovore RNO01 — second data center

This record consolidates 2 research observations while retaining source distinctions, location precision and unresolved fields.

under_constructionproject status
CURRENT_OPERATOR_SECOND_SEPARATE_BUILDING_UNDER_CONSTRUCTIONbest evidence tier
2linked evidence rows
Project facts

Location and operating record

Operator / developerColovore
JurisdictionSparks, NV
AddressNot published
Location precisionlocality
CoordinatesNot published; no coordinate inferred
CapacityNot established
AliasesColovore RNO01 second data center · Colovore RNO01 Building 2
Evidence coverage

What has been researched

Project profile— rows
Intent / permits— rows
Civic / infrastructure0 rows
SITE IDENTITY

Colovore RNO01 — second data center: site identity

Evidence record

Colovore's September 9, 2026 announcement explicitly confirms TWO different data-center buildings at RNO01, one newly opened and a second still under construction. This record is solely the second physical building: CSV3319. The original first building remains canonical colovore-rno01-nv-83e0e081, and RNO02 is a separate site.

Claim classification: Not yet assigned · Verification: first_party_distinct_second_building · Retrieved: 2026-10-31

Limitation: No independent building footprint, address, roof coordinate, second structure MW, metered load or commissioned state.

Open source 1 →

LIFECYCLE

Colovore RNO01 — second data center: lifecycle

Evidence record

First-party September 9, 2026 release: second RNO01 building under construction, with projected February 2027 completion. The first 6 MW completed building is a DIFFERENT canonical facility; neither its 6 MW nor advertised overall 16 MW is attributed to the second.

Claim classification: Not yet assigned · Verification: first_party_construction_as_of_2026_09_09 · Retrieved: 2026-10-31

Limitation: Projected February 2027 is future and uncertain. Do not infer opening, capacity, load or building-specific position.

Open source 1 →

Sources

Evidence and provenance

  • Colovore ↗ · Retrieved 2026-10-31 · FIRST PARTY DISTINCT SECOND BUILDING CONSTRUCTION
    Limitation: Dated September 9, 2026 statement supports second separate RNO01 building under construction. February 2027 is a target, not a completion observation; no second building address, coordinates, commissioning, delivered MW or IT load.
  • Colovore ↗ · Retrieved 2026-10-31 · FIRST PARTY DISTINCT RNO01 VS RNO02 CAMPUS
    Limitation: RNO01 16 MW and two 8 MW hall offerings refer to advertised site design, not measured or assigned second-building IT power; RNO02 is another campus.

Open NV state research →

Colovore RNO01 — second data center Data Center Project | Sparks | Compute Equity Atlas