Compute Equity Atlas
← National map
Source-backed project record · NE

Fortitude Grand Island Facility

This record consolidates 18 research observations while retaining source distinctions, location precision and unresolved fields.

operationalproject status
CORROBORATEDbest evidence tier
18linked evidence rows
Project facts

Location and operating record

Operator / developerFortitude Mining Holdings, Inc. (subsidiary structure tied to Digital Currency Group)
JurisdictionGrand Island, NE
Address380 Museum Drive (just south of the Seedling Mile Road / Museum Drive intersection, east of the JBS plant)
Location precisionstreet address
CoordinatesNot published; no coordinate inferred
CapacityNot established
AliasesFortitude Grand Island Facility · Fortitude Grand Island · Fortitude Mining Grand Island
Evidence coverage

What has been researched

Project profile0 rows
Intent / permits0 rows
Civic / infrastructure2 rows
SOURCE RECORD

Fortitude Grand Island Facility: source record

operational

12 MW is delivered electrical capacity for a Zcash mining facility, recorded as requested_load_mw. Estimated power cost about $0.045/kWh; the load is interruptible and designed to curtail during peak demand. Energization date from the company's own July 28, 2026 press release.

Key data: City of Grand Island municipal electric utility (Utilities Director Ryan Schmitz quoted; interruptible service rate agreement approved by the City Council) | Southwest Power Pool (SPP) | None - facility uses no city water or groundwater

Claim classification: Not yet assigned

Status date: 2026-09

Open source 1

OWNERSHIP AND PROFILE

Fortitude Grand Island Facility: ownership and profile

operational

Developer: Fortitude Mining Holdings, Inc. | Owner: Fortitude Mining Holdings, Inc. | County: Hall | Research region: Central Nebraska

Claim classification: Not yet assigned

Status date: 2026-09

Open source 1

POWER AND GRID

Fortitude Grand Island Facility: power and grid

operational

Key data: Utility: City of Grand Island municipal electric utility (Utilities Director Ryan Schmitz quoted; interruptible service rate agreement approved by the City Council) | Grid area: Southwest Power Pool (SPP) | Requested load MW: 12

Claim classification: Not yet assigned

Status date: 2026-09

Open source 1

operational

The facility is positioned between two solar generation facilities and beside a substation with historically excess capacity, at estimated power costs of about $0.045/kWh, designed to curtail during peak demand; the City of Grand Island's utilities director is quoted.

Key data: ~$0.045/kWh; interruptible

Claim classification: documented_fact · Verification: verified_against_primary_source · Retrieved: 2026-09-14

Status date: 2026-07-28

Open source 1

WATER AND COOLING

Fortitude Grand Island Facility: water and cooling

operational

Key data: Water utility: None - facility uses no city water or groundwater | Water demand: No water use expected | Cooling: Air-cooled (no water use expected) | Wastewater: None

Claim classification: Not yet assigned

Status date: 2026-09

Open source 1

operational

Fortitude states the building is not expected to use any water or to increase ambient sound levels at any adjacent property line.

Key data: No water use expected

Claim classification: proposal_or_announced_commitment · Verification: operator_claim_not_independently_verified · Retrieved: 2026-09-14

Status date: 2026-07-28

Open source 1

PERMITS AND JURISDICTION

Fortitude Grand Island Facility: permits and jurisdiction

operational

Key data: Jurisdictions: City of Grand Island | Hall County | Nebraska

Claim classification: Not yet assigned

Status date: 2026-09

Open source 1

approved

Grand Island issued an RFP in June 2025 with bids due July 8, 2025; the council approved a 10-year land lease at $18,000/year escalating 3% annually, extendable to 20 years, on Sept. 9, 2025, and approved an interruptible service rate agreement 9-0 on June 23, 2026.

Key data: 10-year lease at $18,000/yr; 9-0 rate approval

Claim classification: documented_fact · Verification: single_source · Retrieved: 2026-09-14

Status date: 2026-06-23

Open source 1

CIVIC AND COMMUNITY

Fortitude Grand Island Facility: civic and community

operational

Acoustic study conducted April 17; company states the building is not expected to increase ambient sound levels at any adjacent property line

Claim classification: Not yet assigned

Status date: 2026-09

Open source 1

operational

10-year land lease from the City of Grand Island at $18,000/year escalating 3% per year, extendable to 20 years

Claim classification: Not yet assigned

Status date: 2026-09

Open source 1

ENVIRONMENT AND SITE

Fortitude Grand Island Facility: environment and site

operational

Key data: Surrounding infrastructure: Positioned between two solar generation facilities and beside a substation with historically excess capacity

Claim classification: Not yet assigned

Status date: 2026-09

Open source 1

TIMELINE

Fortitude Grand Island Facility: timeline

operational

City of Grand Island issues an RFP for the site

Claim classification: Not yet assigned

Status date: 2025-06

Open source 1

operational

Bids due

Claim classification: Not yet assigned

Status date: 2025-07-08

Open source 1

operational

Grand Island City Council approves a 10-year land lease at $18,000/year

Claim classification: Not yet assigned

Status date: 2025-09-09

Open source 1

operational

City Council approves an interruptible service rate agreement 9-0

Claim classification: Not yet assigned

Status date: 2026-06-23

Open source 1

operational

Facility energized with 12 MW of power capacity; first greenfield build for Fortitude

Claim classification: Not yet assigned

Status date: 2026-07-28

Open source 1

LOCATION AND SITE

Fortitude Grand Island Facility: location and site

under construction

The 12 MW Fortitude facility is at 380 Museum Drive just south of the Seedling Mile Road / Museum Drive intersection, east of the JBS plant, on a 0.65-acre site, using no city water, groundwater or wastewater.

Key data: 380 Museum Drive; 0.65 acres

Claim classification: documented_fact · Verification: single_source · Retrieved: 2026-09-14

Status date: 2026-06-26

Open source 1

STATUS AND DEVELOPMENT

Fortitude Grand Island Facility: status and development

operational

Fortitude energized the 12 MW Grand Island facility, its first greenfield build, validating electrical infrastructure ahead of full-scale operations.

Key data: 12 MW energized

Claim classification: verified_outcome · Verification: verified_against_primary_source · Retrieved: 2026-09-14

Status date: 2026-07-28

Limitation: Company press release.

Open source 1

Sources

Evidence and provenance

Open NE state research →

Fortitude Grand Island Facility Data Center Project | Grand Island | Compute Equity Atlas