operational
Google announces a new northwest Omaha data center as part of a $750 million Nebraska investment; 261-acre site, up to 1.4 million gross sq ft, up to four stories, including an OPPD switchyard
Claim classification: Not yet assigned
Status date: 2022-04-21
Open source 1 →
operational
Google seeks rezoning of about 187 additional acres, taking the site to roughly 460 acres and more than 2.2 million gross sq ft
Claim classification: Not yet assigned
Status date: 2023-01-03
Open source 1 →
operational
Facility begins operating while construction continues
Claim classification: Not yet assigned
Status date: 2024
Open source 1 →
operational
The Omaha facility began operating in 2024 while construction continued.
Key data: Operating from 2024
Claim classification: documented_fact · Verification: single_source · Retrieved: 2026-09-14
Status date: 2024
Open source 1 →