Project facts

Location and operating record

Operator / developerH5 Data Centers
JurisdictionLa Vista, NE
Address10917 Harry Watanabe Parkway
Location precisionstreet address
CoordinatesNot published; no coordinate inferred
Capacity17.3 MW
AliasesH5 Data Centers Omaha (La Vista) · H5 Omaha · Former Yahoo La Vista campus
Evidence coverage

What has been researched

Project profile0 rows
Intent / permits0 rows
Civic / infrastructure0 rows
SOURCE RECORD

H5 Data Centers Omaha (La Vista): source record

operational

17.3 MW is the operator's marketed critical/IT capacity figure from its own site page; utility not named on the operator page, so left null rather than inferred (La Vista is in OPPD territory but this was not verified for this address).

Key data: Southwest Power Pool (SPP)

Claim classification: Not yet assigned

Status date: 2026-09

Open source 1

OWNERSHIP AND PROFILE

H5 Data Centers Omaha (La Vista): ownership and profile

operational

Owner: H5 Data Centers | County: Sarpy | Research region: Omaha metro / Sarpy County | Tenants/customers: Multi-tenant colocation and wholesale customers

Claim classification: Not yet assigned

Status date: 2026-09

Open source 1

POWER AND GRID

H5 Data Centers Omaha (La Vista): power and grid

operational

Key data: Grid area: Southwest Power Pool (SPP) | IT load MW: 17.3

Claim classification: Not yet assigned

Status date: 2026-09

Open source 1

WATER AND COOLING

H5 Data Centers Omaha (La Vista): water and cooling

operational

Claim classification: Not yet assigned

Status date: 2026-09

Open source 1

PERMITS AND JURISDICTION

H5 Data Centers Omaha (La Vista): permits and jurisdiction

operational

Key data: Jurisdictions: City of La Vista | Sarpy County | Nebraska

Claim classification: Not yet assigned

Status date: 2026-09

Open source 1

TIMELINE

H5 Data Centers Omaha (La Vista): timeline

operational

H5 Data Centers acquires the former Yahoo La Vista campus and markets 234,500 sq ft / 17.3 MW on 32 acres

Claim classification: Not yet assigned

Status date: 2024