Mesa Ordinance No. 5957 defines "Data Center" as a distinct land use and allows City Council to permit data centers via a Planned Area Development (PAD) overlay used with certain industrial districts; absent a waiver, data centers are restricted to General Industrial (GI) and Heavy Industrial (HI) districts, which the staff analysis notes is under 1% of Mesa's land. Waiver applications must be filed within three years and, once granted and applied to the land, run with the land.
Key data: Ordinance No. 5957; data centers limited to GI/HI absent waiver (<1% of city land); waiver must be filed within 3 years
Limitation: Staff analysis: https://mesa.legistar.com/View.ashx?M=F&ID=14316613&GUID=BDA669FE-AA23-446F-836E-8F9A38893914 . An itemized list of individual granted waiver cases was not retrievable — see NOT_FOUND row below.