Project facts

Location and operating record

Operator / developerMeta Platforms, Inc.
JurisdictionSpringfield, NE
AddressLand south of Capehart Road in Springfield (more than 500 acres acquired)
Location precisionparcel or bounded site
CoordinatesNot published; no coordinate inferred
CapacityNot established
AliasesMeta Sarpy Data Center - Springfield expansion · Meta Sarpy Data Center (Springfield portion) · Meta Springfield expansion · Sarpy Data Center ninth building
Evidence coverage

What has been researched

Project profile0 rows
Intent / permits0 rows
Civic / infrastructure0 rows
SOURCE RECORD

Meta Sarpy Data Center - Springfield expansion: source record

under construction

Kept separate because sources describe a distinct municipal jurisdiction (Springfield) and separate land acquisition, but Meta markets the whole thing as one Sarpy Data Center campus - possible duplicate of TEMP-1. No source fetched this session confirms completion of the ninth building, so status remains under construction rather than operational.

Key data: Omaha Public Power District (OPPD) | Southwest Power Pool (SPP) | Metropolitan Utilities District (M.U.D.)

Claim classification: Not yet assigned

Status date: 2026-09

Open source 1

OWNERSHIP AND PROFILE

Meta Sarpy Data Center - Springfield expansion: ownership and profile

under construction

Developer: Meta Platforms, Inc. | Owner: Meta Platforms, Inc. | County: Sarpy | Research region: Omaha metro / Sarpy County | Tenants/customers: Meta Platforms (self-build, own use)

Claim classification: Not yet assigned

Status date: 2026-09

Open source 1

POWER AND GRID

Meta Sarpy Data Center - Springfield expansion: power and grid

under construction

Key data: Utility: Omaha Public Power District (OPPD) | Grid area: Southwest Power Pool (SPP)

Claim classification: Not yet assigned

Status date: 2026-09

Open source 1

WATER AND COOLING

Meta Sarpy Data Center - Springfield expansion: water and cooling

under construction

Key data: Water utility: Metropolitan Utilities District (M.U.D.)

Claim classification: Not yet assigned

Status date: 2026-09

Open source 1

PERMITS AND JURISDICTION

Meta Sarpy Data Center - Springfield expansion: permits and jurisdiction

under construction

Key data: Jurisdictions: City of Springfield | Sarpy County | Nebraska

Claim classification: Not yet assigned

Status date: 2026-09

Open source 1

TIMELINE

Meta Sarpy Data Center - Springfield expansion: timeline

under construction

Meta crosses Capehart Road into Springfield; project renamed Sarpy Data Center

Claim classification: Not yet assigned

Status date: 2021

Open source 1

under construction

Ninth building and an additional $400 million announced; more than 500 acres acquired in Springfield; building due by end of 2024

Claim classification: Not yet assigned

Status date: 2022-07-28

Open source 1

Sources

Evidence and provenance

Open NE state research →