approved_or_permittedproject status
CORROBORATEDbest evidence tier
8linked evidence rows
Project facts

Location and operating record

Operator / developerMicrosoft Corporation
JurisdictionWest Des Moines, IA
AddressNot published
Location precisionparcel or bounded site
CoordinatesNot published; no coordinate inferred
CapacityNot established
AliasesMicrosoft Project Ruthenium Data Center · Project Ruthenium · Microsoft sixth West Des Moines data center
Evidence coverage

What has been researched

Project profile0 rows
Intent / permits0 rows
Civic / infrastructure1 rows
SOURCE RECORD

Microsoft Project Ruthenium Data Center: source record

approved

Business Record: up to four buildings; phase 1 245,000 sq ft, $210M, about 25 full-time jobs; project in Madison County along Veterans Parkway at Woodland Avenue. DCD separately reports a 111-acre 'Project Ruthenium' parcel west of Osmium. Acreage conflict: Business Record ~103 acres cited by secondary aggregator vs DCD 111 acres - not entered. 113 MW figure appears only in iowasaifuture.com (lead only).

Claim classification: Not yet assigned

Status date: 2026-06

Open source 1

OWNERSHIP AND PROFILE

Microsoft Project Ruthenium Data Center: ownership and profile

approved

Developer: Microsoft Corporation | County: Madison | Research region: Des Moines metro / Central Iowa

Claim classification: Not yet assigned

Status date: 2026-06

Open source 1

POWER AND GRID

Microsoft Project Ruthenium Data Center: power and grid

WATER AND COOLING

Microsoft Project Ruthenium Data Center: water and cooling

PERMITS AND JURISDICTION

Microsoft Project Ruthenium Data Center: permits and jurisdiction

approved

Key data: Jurisdictions: West Des Moines | Madison County | IA | Tax incentives: City of West Des Moines development agreement including $15M in city public improvements

Claim classification: Not yet assigned

Status date: 2026-06

Open source 1

CIVIC AND COMMUNITY

Microsoft Project Ruthenium Data Center: civic and community

approved

City to fund about $15M in public improvements; Business Record cites ~$200M of TIF-funded public improvements tied to Microsoft in West Des Moines

Claim classification: Not yet assigned

Status date: 2026-06

Open source 1

TIMELINE

Microsoft Project Ruthenium Data Center: timeline

approved

West Des Moines City Council approved a development agreement with Microsoft for its sixth data center project

Claim classification: Not yet assigned

Status date: 2024-05-20

Open source 1

approved

Additional Microsoft land purchase (Project Ruthenium, 111 acres west of Osmium) reported by DCD

Claim classification: Not yet assigned