Microsoft West Des Moines Data Center Campus (Project Mountain)

This record consolidates 10 research observations while retaining source distinctions, location precision and unresolved fields.

operationalproject status
CORROBORATEDbest evidence tier
10linked evidence rows
Project facts

Location and operating record

Operator / developerMicrosoft Corporation
JurisdictionWest Des Moines, IA
AddressNot published
Location precisionlocality centroid
Coordinates41.549937, -93.781351
CapacityNot established
AliasesMicrosoft West Des Moines Data Center Campus (Project Mountain) · Project Mountain campus · Project Mountain · Microsoft West Des Moines Campus I
Evidence coverage

What has been researched

Project profile0 rows
Intent / permits0 rows
Civic / infrastructure2 rows
SOURCE RECORD

Microsoft West Des Moines Data Center Campus (Project Mountain): source record

operational

Earliest Microsoft campus in West Des Moines (first opened 2012 per WPR). Street address not confirmed by a fetched primary source; secondary Iowa blog (iowasaifuture.com) cites 8855 Grand Ave and ~415-480k sq ft, treated as DISCOVERY_LEAD only and not entered as a street value. Microsoft newsroom describes an Azure AI supercomputer built in Iowa for OpenAI/GPT-4 but does not attribute it to a specific campus. No per-campus MW figure published by Microsoft.

Key data: West Des Moines Water Works

Claim classification: Not yet assigned

Status date: 2026-06

Open source 1

OWNERSHIP AND PROFILE

Microsoft West Des Moines Data Center Campus (Project Mountain): ownership and profile

operational

Developer: Microsoft Corporation | Owner: Microsoft Corporation | County: Dallas | Research region: Des Moines metro / Central Iowa

Claim classification: Not yet assigned

Status date: 2026-06

Open source 1

POWER AND GRID

Microsoft West Des Moines Data Center Campus (Project Mountain): power and grid

operational

Claim classification: Not yet assigned

Status date: 2026-06

Open source 1

WATER AND COOLING

Microsoft West Des Moines Data Center Campus (Project Mountain): water and cooling

operational

Key data: Water utility: West Des Moines Water Works | Water source: Municipal supply (West Des Moines Water Works); Microsoft-funded aquifer storage and recovery well project | Water demand: Microsoft's West Des Moines operations used 68.5 million gallons in 2024; agreement with West Des Moines Water Works allows up to 5 million gallons per day

Claim classification: Not yet assigned

Status date: 2026-06

Open source 1

PERMITS AND JURISDICTION

Microsoft West Des Moines Data Center Campus (Project Mountain): permits and jurisdiction

operational

Key data: Jurisdictions: West Des Moines | Dallas County | IA | Tax incentives: City of West Des Moines TIF-funded public improvements (~$200M cited citywide for Microsoft projects)

Claim classification: Not yet assigned

Status date: 2026-06

Open source 1

CIVIC AND COMMUNITY

Microsoft West Des Moines Data Center Campus (Project Mountain): civic and community

operational

Approximately $182M in city street and utility improvements tied to Microsoft development (Microsoft newsroom)

Claim classification: Not yet assigned

Status date: 2026-06

Open source 1

operational

Microsoft paid for a West Des Moines water tower and ~$25M of West Des Moines Water Works improvements

Claim classification: Not yet assigned

Status date: 2026-06

Open source 1

ENVIRONMENT AND SITE

Microsoft West Des Moines Data Center Campus (Project Mountain): environment and site

operational

Key data: Surrounding infrastructure: West Des Moines Water Works 2-million-gallon storage tank (2023)

Claim classification: Not yet assigned

Status date: 2026-06

Open source 1

TIMELINE

Microsoft West Des Moines Data Center Campus (Project Mountain): timeline

operational

First Microsoft West Des Moines data center campus opened

Claim classification: Not yet assigned

Status date: 2012

Open source 1

operational

WPR reports Microsoft operates five West Des Moines campuses with a sixth approved

Claim classification: Not yet assigned

Status date: 2026

Open source 1

Sources

Evidence and provenance

Open IA state research →

Microsoft West Des Moines Data Center Campus (Project Mountain) Data Center Project | West Des Moines | Compute Equity Atlas