PowerConneX I & II (120 / 216 MW)

This canonical record consolidates 3 source-backed observations without discarding aliases, limitations or unresolved dimensions.

unknownproject status
VERIFIED_PRIMARYbest evidence tier
3linked evidence rows
Project facts

Location and operating record

Operator / developerNot established in current evidence
JurisdictionLicking County / New Albany, OH
Address6 acres northwest of the Route 161 and Mink Street intersection
Location precisionexact coordinate
Coordinates40.0877294, -82.722445
CapacityNot established
AliasesPowerConneX I & II · PowerConneX I & II (120 / 216 MW)
Evidence coverage

What has been researched

Project profile3 rows
Intent / permits0 rows
Civic / infrastructure0 rows
EXACT LOCATION

PowerConneX I & II (120 / 216 MW): exact location

VERIFIED_PRIMARY

EdgeConneX's project page places the New Albany Energy Center on ~48.6 acres northwest of the Route 161 and Mink Street intersection; GEM records coordinates.

Key data: ~48.6 ac NW of Rt 161 & Mink St; 40.0877294, -82.722445

Limitation: Coordinates are GEM-derived (DISCOVERY_LEAD): https://www.gem.wiki/PowerConneX_I_and_II_New_Albany_Energy_Center

Open source →

OWNERSHIP CHAIN / POWER SUPPLIER

PowerConneX I & II (120 / 216 MW): ownership chain / power supplier

VERIFIED_PRIMARY

Owners of record are PowerConneX Inc. and Powerconnex New Albany 2, LLC, EdgeConneX affiliates under parent EQT; OPSB minutes confirm Powerconnex New Albany 2, LLC's certificate case for a gas-fired generation facility serving a data center in New Albany.

Key data: Case 25-302-EL-BGN (Powerconnex New Albany 2, LLC); parent EQT

Limitation: EQT parentage is from GEM/trade reporting, not the OPSB minutes.

Open source →

GENERAL CONTACT

PowerConneX I & II (120 / 216 MW): general contact

VERIFIED_PRIMARY

EdgeConneX publishes a project phone line and email for the New Albany Energy Center.

Key data: (703) 935-1980; pcxenergynewalbany@edgeconnex.com

Limitation:

Open source →

Sources

Evidence and provenance

  • EdgeConneX · VERIFIED PRIMARY
    Limitation: Coordinates are GEM-derived (DISCOVERY_LEAD): https://www.gem.wiki/PowerConneX_I_and_II_New_Albany_Energy_Center
  • Ohio Power Siting Board · VERIFIED PRIMARY
    Limitation: EQT parentage is from GEM/trade reporting, not the OPSB minutes.

Open OH state research →