Compute Equity Atlas
← National map
Source-backed project record · NM

Project Jupiter (Stargate Santa Teresa Campus)

This record consolidates 8 research observations while retaining source distinctions, location precision and unresolved fields.

under_constructionproject status
SOURCE_BACKEDbest evidence tier
8linked evidence rows
Project facts

Location and operating record

Operator / developerNot established in current evidence
JurisdictionSanta Teresa CDP, NM
AddressNot published
Location precisionlocality centroid
Coordinates31.87136, -106.673424
Capacity2500 MW
AliasesProject Jupiter (Stargate Santa Teresa Campus)
Evidence coverage

What has been researched

Project profile0 rows
Intent / permits0 rows
Civic / infrastructure0 rows
SOURCE RECORD

Project Jupiter (Stargate Santa Teresa Campus): source record

REVIEWED PROJECT UPDATES

Project Jupiter (Stargate Santa Teresa Campus): reviewed project updates

Source observation

Oracle's September 14, 2026 statement distinguishes Project Jupiter's data-center campus from the adjacent proposed microgrid and says campus construction is continuing.

Key data: Oracle identifies the stayed proceeding as the microgrid air-permit application rather than the campus building permits. The microgrid is not another data-center building.

Claim classification: Attributed source observation · Verification: Listed fields reviewed; not a site inspection · Retrieved: 2026-10-03

Status date: 2026-09-14

Limitation: This is an attributed developer statement, not an independent legal determination. No whole-campus cancellation or force-majeure conclusion is adopted.

Open source 1 →

OWNERSHIP AND PROFILE

Project Jupiter (Stargate Santa Teresa Campus): ownership and profile

POWER AND GRID

Project Jupiter (Stargate Santa Teresa Campus): power and grid

under_construction

Key data: Gross MW: 2500

Claim classification: Not yet assigned

Open source 1 →

WATER AND COOLING

Project Jupiter (Stargate Santa Teresa Campus): water and cooling

PERMITS AND JURISDICTION

Project Jupiter (Stargate Santa Teresa Campus): permits and jurisdiction

Sources

Evidence and provenance

  • Source record ↗ · SOURCE BACKED
  • oracle.com ↗ · Retrieved 2026-10-03 · SOURCE BACKED
    Limitation: This is an attributed developer statement, not an independent legal determination. No whole-campus cancellation or force-majeure conclusion is adopted.

Open NM state research →

Project Jupiter (Stargate Santa Teresa Campus) Data Center Project | Santa Teresa CDP | Compute Equity Atlas