Aberdeen Data Center

Aberdeen, OH

Reported status: proposed

Reported capacity: 400.00 MW (scope and operation unverified)

Exact location not published.

Original source · 2026-06-18

research-final:OH:b1643b954c3543113643
Accepted facility identity linked

ark data centers - Akron,OH

Akron, OH · ark data centers

Reported status: operational

Exact location not published.

Original source · 2025-09-26

Read 1 source findings (2026-10-30)

Operator confirms two active Akron facilities. Current carrier directory binds both Akron I and II to the same 191 East Miller address; publish one physical campus, not duplicate building-level pins. Census matches full street and ZIP. Evidence

Existing project record

research-final:OH:65c49dac286edeaef265
Awaiting source review

Ark Data Centers Akron I (fka Involta)

Akron, OH · Ark Data Centers (formerly Involta)

Reported status: operational

Reported capacity: 1 MW operational (scope and operation unverified)

Source reference: address match (exact): 191 E MILLER AVE, AKRON, OH, 44301. Census Geocoder; not a verified facility pin.

Original source · 2026-07-25

research-final:OH:9bebe348883a95203b63
Awaiting source review

Ark Data Centers Akron II (fka Involta)

Akron, OH · Ark Data Centers (formerly Involta)

Reported status: operational

Reported capacity: 1 MW operational (scope and operation unverified)

Source reference: address match (exact): 191 E MILLER AVE, AKRON, OH, 44301. Census Geocoder; not a verified facility pin.

Original source · 2026-09-21

research-final:OH:56e4ef7f06b49e8dcf0e
Awaiting source review

BIT Mining / Viking Data Centers — Akron

Akron, OH · BIT Mining / Viking Data Centers

Reported status: operational

Reported capacity: 150 MW planned; 83 MW operational (scope and operation unverified)

Source reference: address match (exact): 428 SEIBERLING ST, AKRON, OH, 44306. Census Geocoder; not a verified facility pin.

Original source · 2026-08-16

research-final:OH:b1a2911c196d84fd6580
Accepted facility identity linked

Cogent Data Center Akron

Akron, OH · Cogent Communications

Reported status: operational

Reported capacity: 5 MW operational (scope and operation unverified)

Exact location not published.

Original source · 2026-08-02

Read 1 source findings (2026-10-30)

Current operator facility page and wholesale brochure confirm Akron data-center identity at full address. Census matches. Marketing capacity is not treated as measured operating load. Evidence

Existing project record

research-final:OH:b3cadf6991f10c1e0eb4
Awaiting source review

Involta-Akron

Akron, OH

Reported status: operational

Exact location not published.

Original source · 2026-06-17

research-final:OH:7381bae13cfb736df323
Awaiting source review

Lumen Akron 2

Akron, OH · Lumen Technologies

Reported status: operational

Reported capacity: 3 MW planned (scope and operation unverified)

Exact location not published.

Original source · 2026-08-16

research-final:OH:caf8f3de4411509aefb5
Awaiting source review

Viking Data Centers

Akron, OH

Reported status: operational

Reported capacity: 150.00 MW (scope and operation unverified)

Exact location not published.

Original source · 2026-06-18

research-final:OH:21092ee92d97337e01d9
Awaiting source review

Ashville Campus

Ashville, OH · EdgeConneX

Reported status: proposed

Exact location not published.

Original source · 2026-08-08

research-final:OH:e050948f639d7d9ab383
Awaiting source review

EdgeConneX Ashville Data Center Campus

Ashville, OH · EdgeConneX

Reported status: proposed

Reported capacity: 1.8 GW (scope and operation unverified)

Exact location not published.

Original source · 2026-07-17

research-final:OH:8ab0e11253e4130afa24
Awaiting source review

Project Triton

Barberton, OH

Reported status: proposed

Exact location not published.

Original source · 2026-06-18

research-final:OH:f6ce20bdeb49b2c6d3d8
Accepted facility identity linked

Cipher Digital Ulysses

Beverly, OH · Cipher Digital (formerly Cipher Mining)

Reported status: proposed

Reported capacity: 200 MW planned (scope and operation unverified)

Exact location not published.

Original source · 2026-08-26

Read 1 source findings (2026-10-30)

Current operator portfolio lists Ulysses in future development pipeline. Company acquisition release confirms Ohio identity, but does not independently bind Beverly or a street address. Publish state-level identity only; no town inferred from archive and no utility-capacity-to-IT-load conversion. Evidence

Existing project record

research-final:OH:a1d8f499f0460ea6e307
Awaiting source review

HashWorks Powered Land — Waterford Site

Beverly, OH · HashWorks Powered Land Waterford LLC (land entity tied to Cipher Digital / Sabre 56)

Reported status: proposed

Reported capacity: 200 MW planned (scope and operation unverified)

Exact location not published.

Original source · 2026-09-21

research-final:OH:6073cd107149643a1c2f
Awaiting source review

Project Andromeda (Oxford Township)

Bloomingville, OH · AVAIO Digital

Reported status: proposed

Reported capacity: 250 MW planned (scope and operation unverified)

Exact location not published.

Original source · 2026-10-14

research-final:OH:1d050ad2ea671ac712ff
Accepted facility identity linked

Encore Technologies BLU1 (Blue Ash)

Blue Ash, OH · Encore Technologies

Reported status: operational

Exact location not published.

Original source · 2026-09-09

Read 1 source findings (2026-10-30)

Current operator confirms Blue Ash among four active data centers; current published 2026 policy scope identifies full facility address. Census exact normalized street and ZIP match. Evidence

Existing project record

research-final:OH:60aa6582a8d9a3455309
Awaiting source review

Carrier Services Group

Boardman, OH

Reported status: existing (mapped; status unverified)

Exact location not published.

Original source · 2026-06-14

research-final:OH:25327f0e48ea84b6b0a1
Awaiting source review

Datacenter

Bowling Green, OH · Bowling Green State University

Reported status: existing (mapped; status unverified)

Exact location not published.

Original source · 2026-10-28

research-final:OH:3a25d14c11447ffaa890
Awaiting source review

Meta Bowling Green (Project Accordion)

Bowling Green, OH · Meta

Reported status: under construction

Reported capacity: 514.00 MW (scope and operation unverified)

Exact location not published.

Original source · 2026-10-22

research-final:OH:2e7bf5cc6d2473e3d396
Awaiting source review

Meta Bowling Green Data Center

Bowling Green, OH · Meta

Reported status: under construction

Reported capacity: 350 MW (scope and operation unverified)

Approximate locality: approximate: Census 2024 Gazetteer place centroid for Bowling Green. Census 2024 Gazetteer centroid; not a verified facility pin.

Original source · 2026-07-19

research-final:OH:5aafc9c01632e2cb27cb
Awaiting source review

Cleveland Clinic Data Center

Brecksville, OH

Reported status: existing (EPA facility record; status unverified)

Regulatory reference: FRS facility point (stated accuracy 30 m). EPA FRS/ECHO; not a verified facility pin.

Original source · 2026-10-28

research-final:OH:6fb67cc3b60a0d98e689
Awaiting source review

Bristolville AI Data Center

Bristolville, OH · Clean Capital Partners; Tecfusions

Reported status: proposed

Approximate locality: approximate: Census 2024 Gazetteer county centroid for Trumbull County. Census 2024 Gazetteer centroid; not a verified facility pin.

Original source · 2026-07-17

research-final:OH:7de50d4b03b580dcf14f
Accepted facility identity linked

Ark Data Centers Canton

Canton, OH · Ark Data Centers

Reported status: operational

Reported capacity: 1.50 MW (scope and operation unverified)

Exact location not published.

Original source · 2026-10-14

Read 1 source findings (2026-10-30)

Current operator facility page confirms operating Canton colocation. SecureData 365 is an old-name alias, not an additional site. Exact address and geometry remain held pending primary binding. Evidence

Existing project record

research-final:OH:3a8737fc9fe305953934
Accepted facility identity linked

DAMAC Digital Canton Orchard View Data Center

Canton, OH · DAMAC Digital

Reported status: proposed

Reported capacity: 225 MW planned (scope and operation unverified)

Exact location not published.

Original source · 2026-10-15

Read 1 source findings (2026-10-30)

Current developer project website identifies proposed Orchard View data center in Canton. Meeting address at community center is not the facility address. No inferred parcel coordinates, capacity or operational status. Evidence

Existing project record

research-final:OH:1e4bc836651e5f5f334b
Accepted facility identity linked

LSTI 401 Market

Canton, OH · LightSpeed Technologies, LLC

Reported status: operational

Exact location not published.

Original source · 2026-06-17

Read 1 source findings (2026-10-30)

Current operator lists 401 Market among its data-center services and binds that named location to full street and ZIP. Census matches. Other carrier-connected buildings are not assumed to be owned data centers. Evidence

Existing project record

research-final:OH:52158358fca3b8da59c1
Accepted facility identity linked

Midwest Digital Gateway (Central Avenue SE, Canton)

Canton, OH · Corscale

Reported status: proposed

Reported capacity: 312 MW planned (scope and operation unverified)

Exact location not published.

Original source · 2026-10-15

Read 1 source findings (2026-10-30)

Current developer explicitly identifies four-building Canton campus and states preliminary site work, construction and operations have not started. Admit one proposed campus, distinct from DAMAC Orchard View. General neighborhood illustration is not verified geography. Evidence

Existing project record

research-final:OH:b2a14d83f0f001dba830
Awaiting source review

Perry Township Data Center

Canton, OH · Panattoni Development Company

Reported status: under construction

Reported capacity: 240 MW planned (scope and operation unverified)

Exact location not published.

Original source · 2026-09-23

research-final:OH:03c0ca111e370192f3cd
Awaiting source review

Project Shelby

Canton, OH · Panattoni Development Co.

Reported status: proposed

Reported capacity: 320 MW planned (scope and operation unverified)

Exact location not published.

Original source · 2026-10-15

research-final:OH:6d0bed979be0c11b7d0c
Awaiting source review

SecureData 365

Canton, OH · SecureData 365

Reported status: operational

Exact location not published.

Original source · 2025-09-26

research-final:OH:62b27f1c9144734cb723
Awaiting source review

Aligned HPC Campus at Former Pixelle Paper Mill (Chillicothe)

Chillicothe, OH · Aligned Data Centers (in partnership with U.S. Paper Mill LLC / U.S. Medical Glove Company)

Reported status: proposed

Exact location not published.

Original source · 2026-09-09

research-final:OH:12cc17149d25a08f78bb