Compute Equity Atlas
State research database

All supplied research, searchable

6,466 source records across 50 states and Washington, DC. Records include proposals, existing facilities, regulatory references, expansions and possible duplicates. Reported status and capacity are source claims, not certified current operation or measured demand.

National map

6,466 matching source records

Snapshot: 2026-10-28. Review the linked evidence before relying on a claim. Related records and expansions must not be counted as additional facilities.

Awaiting source review

Ross Stores Rock Hill Data Center

Rock Hill, SC · Ross Stores

Reported status: operational

Reported capacity: 2 MW operational (scope and operation unverified)

Exact location not published.

Original source · 2026-10-27

research-final:SC:d2281c57d1091a40f56f
Awaiting source review

Qts Clt1 Campus

Rockhill, SC

Reported status: approved/permitted (EPA air-permit record)

Exact location not published.

Original source · 2026-10-28

research-final:SC:678f524d59311ecade2c
Awaiting source review

Rhodes Technology Park

Smoaks, SC · Eagle Rock Partners

Reported status: proposed

Reported capacity: 1000 MW planned (scope and operation unverified)

Exact location not published.

Original source · 2026-10-27

research-final:SC:6d80adeab2809aacefce
Accepted facility identity linked

DartPoints Spartanburg Data Center (SPA01)

Spartanburg, SC · DartPoints

Reported status: operational

Reported capacity: 1.6 MW operational (scope and operation unverified)

Exact location not published.

Original source · 2026-09-22

Read 1 source findings (2026-10-29)

Current operator identifies staffed colocation at 5700 North Blackstock Road. Evidence

Existing project record

research-final:SC:3227f613f6aae44202bb
Awaiting source review

DartPoints Spartanburg, SC - SPA1

Spartanburg, SC · DartPoints, LLC

Reported status: operational

Exact location not published.

Original source · 2026-06-17

research-final:SC:2aaa158ca182a0f687a1
Awaiting source review

Greenidge Spartanburg (South Carolina)

Spartanburg, SC · Greenidge Generation

Reported status: cancelled

Reported capacity: 100 MW planned (scope and operation unverified)

Exact location not published.

Original source · 2026-09-10

research-final:SC:5c5f2f49d33a002cfdbd
Awaiting source review

LightHouse Data Centers Spartanburg 300 Jones Road Campus

Spartanburg, SC · LightHouse Data Centers; The Lightstone Group; Wharton Digital

Reported status: proposed

Reported capacity: 60 MW (scope and operation unverified)

Source reference: address match (exact): 300 JONES RD, SPARTANBURG, SC, 29307. Census Geocoder; not a verified facility pin.

Original source · 2026-06-15

research-final:SC:912c3c6e8a8be2afe795
Awaiting source review

Project Moc-1 (NorthMark Strategies)

Spartanburg, SC · NorthMark Strategies; Valara Holdings

Reported status: under construction

Reported capacity: 457 MW (scope and operation unverified)

Exact location not published.

Original source · 2026-07-17

research-final:SC:2ab8cbcb91f4aa184ef2
Awaiting source review

Union - Data Center Phase I Design

Spartanburg, SC

Reported status: existing (EPA facility record; status unverified)

Regulatory reference: FRS facility point (stated accuracy 30 m). EPA FRS/ECHO; not a verified facility pin.

Original source · 2026-10-28

research-final:SC:ba624be0b9b4823ef7ab
Awaiting source review

Valara Holdings High Performance Compute Center

Spartanburg, SC · Valara Holdings (NorthMark Strategies)

Reported status: under construction

Regulatory reference: FRS facility point (stated accuracy 30 m). EPA FRS/ECHO; not a verified facility pin.

Original source · 2026-10-11

research-final:SC:8d49defc67f83f5e39d6
Awaiting source review

Google datacenter

St. George, SC

Reported status: existing (mapped; status unverified)

Exact location not published.

Original source · 2026-10-28

research-final:SC:f3e91ed6a8d7359a685e
Awaiting source review

Google Winding Woods Commerce Park Data Center

St. George, SC · Google LLC

Reported status: under construction

Reported capacity: 236 MW (scope and operation unverified)

Exact location not published.

Original source · 2026-02-05

research-final:SC:2302da1384c2beca9b81
Awaiting source review

Project Alpaca Union County Data Center

Union, SC · Volt Edge Energy

Reported status: proposed

Reported capacity: 49 MW (scope and operation unverified)

Exact location not published.

Original source · 2026-09-22

research-final:SC:de7be90d6d582a3812bd
Awaiting source review

Project Boulder

Walterboro, SC · Eagle Rock Partners

Reported status: proposed

Reported capacity: 1000 MW planned (scope and operation unverified)

Exact location not published.

Original source · 2026-09-23

research-final:SC:230868b945b388f48ab6
Awaiting source review

Walterboro Data Center

Walterboro, SC · Eagle Rock Partners

Reported status: proposed

Reported capacity: 1000.00 MW (scope and operation unverified)

Exact location not published.

Original source · 2026-06-18

research-final:SC:71591bc760e5cb3a49cb
Awaiting source review

Eagle Rock Partners Colleton County Data Center Campus

Walterboro area, SC · Eagle Rock Partners; Thomas & Hutton; Weyerhaeuser Company

Reported status: proposed

Reported capacity: 1.0 GW (scope and operation unverified)

Approximate locality: approximate: Census 2024 Gazetteer place centroid for Walterboro. Census 2024 Gazetteer centroid; not a verified facility pin.

Original source · 2026-06-15

research-final:SC:d79373e8605bc25b1562
Awaiting source review

QTS Charlotte (CTL1)

York, SC · QTS Realty Trust, Inc.

Reported status: operational

Exact location not published.

Original source · 2025-10-20

research-final:SC:184b99e7554f9b8c1f72
Awaiting source review

QTS York County Data Center Campus

York County (unincorporated), SC · QTS Realty Trust; Blackstone; Gilbane

Reported status: under construction

Reported capacity: 702 MW (scope and operation unverified)

Approximate locality: approximate: Census 2024 Gazetteer county centroid for York County. Census 2024 Gazetteer centroid; not a verified facility pin.

Original source · 2026-07-17

research-final:SC:334871df7d3fe50705b0
Awaiting source review

Dorchester County Google Datacenter

, SC

Reported status: existing (mapped; status unverified)

Exact location not published.

Original source · 2026-10-28

research-final:SC:fb6e098eea0e7fe8e340
Awaiting source review

Project Boulder

, SC · Eagle Rock Partners

Reported status: proposed

Reported capacity: 1000 MW planned (scope and operation unverified)

Exact location not published.

Original source · 2026-10-22

research-final:SC:e4649da8957fb6d565c1
Awaiting source review

Savannah River Site AI Data Center (Amentum)

, SC · Amentum

Reported status: proposed

Reported capacity: 1000 MW planned (scope and operation unverified)

Exact location not published.

Original source · 2026-10-27

research-final:SC:9d91c8bc14b0d2a914f6
Accepted facility identity linked

EROS Data Center

Baltic, SD

Reported status: existing (mapped; status unverified)

Exact location not published.

Original source · 2026-10-28

Read 1 source findings (2026-10-29)

Current USGS page confirms continuing EROS archive and data-processing operations. Its 2025 account explicitly describes supercomputers and storage racks inside the on-site computer room. Official locations page supplies the address. Census returned no match; no point published. Evidence

Existing project record

research-final:SD:b678106c35882e4f8bfa
Accepted facility identity linked

Sequitor Edge Brookings Research Park Data Center

Brookings, SD · Sequitor Edge

Reported status: proposed

Reported capacity: 2 MW (scope and operation unverified)

Approximate locality: approximate: Census 2024 Gazetteer place centroid for Brookings. Census 2024 Gazetteer centroid; not a verified facility pin.

Original source · 2026-06-15

Read 1 source findings (2026-10-30)

Developer confirms planned Brookings center alongside Rapid City project. City February 24 minutes reject requested sales-tax incentive, not the entire project. No current commissioning or exact approved site geometry verified. Evidence

Existing project record

research-final:SD:6b9d869e14cde32bad66
Awaiting source review

ADP South Dakota

Crooks, SD

Reported status: existing (mapped; status unverified)

Exact location not published.

Original source · 2026-06-14

research-final:SD:8a97187ba3f12a495ac2
Awaiting source review

Leola Data Center

Leola, SD · Leola Data Center LLC; Montana-Dakota Utilities Co.

Reported status: proposed

Reported capacity: 50 MW (scope and operation unverified)

Approximate locality: approximate: Census 2024 Gazetteer place centroid for Leola. Census 2024 Gazetteer centroid; not a verified facility pin.

Original source · 2026-07-19

research-final:SD:3b5f46521b54638f8d34
Awaiting source review

Leola Data Center

Leola, SD · Leola Data Center, LLC

Reported status: proposed

Reported capacity: 50 MW planned (scope and operation unverified)

Source reference: address match (exact): 11641 358TH AVE, LEOLA, SD, 57456. Census Geocoder; not a verified facility pin.

Original source · 2026-10-27

research-final:SD:3c04e8e3df415b86dd6d
Awaiting source review

Simple Mining Madison Bitcoin Hosting Site

Madison, SD · Simple Mining LLC

Reported status: approved/permitted

Reported capacity: 10 MW planned (scope and operation unverified)

Exact location not published.

Original source · 2026-10-10

research-final:SD:dd967be502720aa59545
Awaiting source review

TierPoint Sioux Falls - East (SFE) — existing data-centre and colocation operations

Meadow View Addition, SD · TierPoint

Reported status: operational

Exact location not published.

Original source · 2026-09-03

research-final:SD:e8b63f6013318fd29a16
Awaiting source review

Data Center

Mitchell, SD

Reported status: existing (mapped; status unverified)

Exact location not published.

Original source · 2026-10-28

research-final:SD:10946b01059fbc27f214
Awaiting source review

Big Watt Digital Sully Buttes Mining Facility

Onida, SD · Big Watt Digital

Reported status: operational

Reported capacity: 300 MW planned; 30 MW operational (scope and operation unverified)

Exact location not published.

Original source · 2026-08-05

research-final:SD:757fb18fc4f45dfbffef
Research database | Compute Equity Atlas