Compute Equity Atlas
State research database

All supplied research, searchable

6,466 source records across 50 states and Washington, DC. Records include proposals, existing facilities, regulatory references, expansions and possible duplicates. Reported status and capacity are source claims, not certified current operation or measured demand.

National map

6,466 matching source records

Snapshot: 2026-10-28. Review the linked evidence before relying on a claim. Related records and expansions must not be counted as additional facilities.

Awaiting source review

Lawrenceburg Flatwoods Road Data Center

Lawrenceburg, TN

Reported status: proposed

Reported capacity: 5 MW (scope and operation unverified)

Exact location not published.

Original source · 2026-06-15

research-final:TN:ec1682f7d436ea798cfa
Awaiting source review

CleanSpark Lenoir City Bitcoin Mining Facility

Lenoir City, TN · CleanSpark, Inc.

Reported status: operational

Reported capacity: 40 MW planned; 20 MW operational (scope and operation unverified)

Exact location not published.

Original source · 2026-09-09

research-final:TN:25ceb0dab87b51bff539
Accepted facility identity linked

LCUB Data Center

Lenoir City, TN · Lenoir City Utilities Board

Reported status: operational

Exact location not published.

Original source · 2026-04-28

Read 1 source findings (2026-10-30)

Current utility operator markets active colocation at its Lenoir City facility. Operator procurement notice binds the data center to its on-site street address. Archive row 4412 is the same facility. Census street-range interpolation is not a rooftop point. Evidence

Existing project record

research-final:TN:d51e3ccb7ef742a64f2b
Awaiting source review

LCUB Data Center (Lenoir City Utilities Board)

Lenoir City, TN · Lenoir City Utilities Board

Reported status: operational

Exact location not published.

Original source · 2026-09-21

research-final:TN:227fff2ae057f5c16a4c
Awaiting source review

CleanSpark Limestone Bitcoin Mining Facility (closed 2026)

Limestone, TN · CleanSpark, Inc.

Reported status: cancelled

Exact location not published.

Original source · 2026-09-09

research-final:TN:6578b25177a00a4aee90
Awaiting source review

Arnold Air Force Base Data Center

Manchester, TN

Reported status: proposed

Exact location not published.

Original source · 2026-06-18

research-final:TN:497e1ee9c34b1484b46f
Awaiting source review

CleanSpark Maynardville Bitcoin Mining Facility

Maynardville, TN · CleanSpark, Inc.

Reported status: operational

Exact location not published.

Original source · 2026-09-09

research-final:TN:d3ce24230eb39072d63c
Awaiting source review

Hixson Data Center

McMinnville, TN · Hixson Data Center

Reported status: proposed

Reported capacity: 25 MW (scope and operation unverified)

Exact location not published.

Original source · 2026-07-17

research-final:TN:2db373346a91558fb394
Awaiting source review

Litewire McMinnville (former A.O. Smith Building)

McMinnville, TN · Litewire

Reported status: operational

Exact location not published.

Original source · 2026-09-21

research-final:TN:0153e072a91458edcaef
Awaiting source review

5C MEM01 Memphis (former Fred's headquarters)

Memphis, TN · 5C Data Centers

Reported status: operational

Reported capacity: 15 MW planned; 20 MW operational (scope and operation unverified)

Source reference: address match (exact): 4300 GETWELL RD, MEMPHIS, TN, 38118. Census Geocoder; not a verified facility pin.

Original source · 2026-10-11

research-final:TN:0e80fb8bc836778b2ef5
Awaiting source review

5C MEM01 Memphis Data Center

Memphis, TN · 5C Data Centers; 5C Group

Reported status: proposed

Reported capacity: 64 MW (scope and operation unverified)

Regulatory reference: FRS facility point (stated accuracy 50 m). EPA FRS/ECHO; not a verified facility pin.

Original source · 2026-07-17

research-final:TN:17c054d44f1aa7280530
Awaiting source review

Connect Data Centers Memphis (3900 S. Mendenhall Road)

Memphis, TN · Connect Data Centers (Oppidan Investment Company)

Reported status: operational

Exact location not published.

Original source · 2026-09-21

research-final:TN:5d686fe946b07a59abd1
Accepted facility identity linked

DataBank MEM1 (Memphis)

Memphis, TN · DataBank

Reported status: operational

Reported capacity: 0.45 MW operational (scope and operation unverified)

Exact location not published.

Original source · 2026-09-21

Read 1 source findings (2026-10-29)

Current operator verifies operating Memphis colocation at 7620 Appling Center Drive. Distinct from the generic new-build Memphis permit record and xAI campuses. Evidence

Existing project record

research-final:TN:ccad764477389261660c
Awaiting source review

Digital Asset Data Center

Memphis, TN

Reported status: existing (EPA facility record; status unverified)

Exact location not published.

Original source · 2026-10-28

research-final:TN:439ebd39fc7c695966f6
Accepted facility identity linked

EdgeConneX Memphis (EDCMEM01)

Memphis, TN · EdgeConneX

Reported status: operational

Exact location not published.

Original source · 2026-09-14

Read 1 source findings (2026-10-30)

Current 2026 operator data sheet confirms operating MEM01 colocation facility. Indexed operator 2024 data sheet supplies street address and unit 6; no electrical nameplate figures inferred as operating load. Census street-range point is not a surveyed unit location. Evidence

Existing project record

research-final:TN:e35e414c107e9c30033d
Accepted facility identity linked

Expedient Memphis (MEM1)

Memphis, TN · Expedient

Reported status: operational

Reported capacity: 1.5 MW operational (scope and operation unverified)

Exact location not published.

Original source · 2026-09-21

Read 1 source findings (2026-10-29)

Current operator confirms operating MEM1 at 3180 Players Lane, distinct from DataBank MEM1 at Appling Center Drive. Evidence

Existing project record

research-final:TN:d0f17a08ef87a44c5763
Awaiting source review

Holiday Inn Data Center-Memphis

Memphis, TN

Reported status: existing (EPA facility record; status unverified)

Exact location not published.

Original source · 2026-10-28

research-final:TN:3dff4ce464d2594c799a
Awaiting source review

Lumen Memphis (3993 Crowfarn Drive) — Level(3)

Memphis, TN · Lumen Technologies

Reported status: operational

Exact location not published.

Original source · 2026-09-21

research-final:TN:e0cc4846f9736a593844
Awaiting source review

Merkle Standard Memphis (4545 South Mendenhall Road)

Memphis, TN · Merkle Standard

Reported status: operational

Source reference: address match (exact): 4545 S MENDENHALL RD, MEMPHIS, TN, 38141. Census Geocoder; not a verified facility pin.

Original source · 2026-09-14

research-final:TN:19ed290f45ba516ce2cd
Awaiting source review

Minihard

Memphis, TN · xAI

Reported status: under construction

Source reference: address match (exact): 5414 TULANE RD, MEMPHIS, TN, 38109. Census Geocoder; not a verified facility pin.

Original source · 2026-09-13

research-final:TN:746db5b3e6ea3c62fd1e
Awaiting source review

Neural Nexus Innovation District

Memphis, TN · Legacy Power Capital

Reported status: proposed

Exact location not published.

Original source · 2026-09-13

research-final:TN:0b5637e0e8b2c165721f
Awaiting source review

Oppidan Data Center

Memphis, TN

Reported status: existing (EPA facility record; status unverified)

Exact location not published.

Original source · 2026-10-28

research-final:TN:9c554daf9fda39fd12ea
Awaiting source review

The STEM Practice Sycamore View AI Data Center

Memphis, TN · Golden Acquisitions / The STEM Practice

Reported status: under construction

Reported capacity: 9 MW planned (scope and operation unverified)

Exact location not published.

Original source · 2026-09-21

research-final:TN:6845044c54aac76af48d
Awaiting source review

xAI Colossus

Memphis, TN · xAI

Reported status: operational

Reported capacity: 250 MW planned (scope and operation unverified)

Exact location not published.

Original source · 2026-09-22

research-final:TN:ba5f6e2bd23a94c3eea0
Awaiting source review

xAI Colossus Supercomputer

Memphis, TN · xAI; MZX Tech

Reported status: operational (expansion)

Reported capacity: 1.6 GW (scope and operation unverified)

Exact location not published.

Original source · 2026-07-17

research-final:TN:cf542e2fdfdf145f6720
Awaiting source review

Tva - Data Center

Middle Valley, TN

Reported status: existing (EPA facility record; status unverified)

Exact location not published.

Original source · 2026-10-28

research-final:TN:ba17c1b16b7211dfa8f2
Awaiting source review

CleanSpark Mountain City Bitcoin Mining Facility

Mountain City, TN · CleanSpark, Inc.

Reported status: proposed

Reported capacity: 30 MW planned (scope and operation unverified)

Exact location not published.

Original source · 2026-09-09

research-final:TN:43cb599b211051c91ee0
Awaiting source review

Data Suites Murfreesboro

Murfreesboro, TN · Data Suites

Reported status: operational

Reported capacity: 2 MW operational (scope and operation unverified)

Exact location not published.

Original source · 2026-09-13

research-final:TN:7d025cedde53ae73c38d
Awaiting source review

BNY Mellon Tennessee Processing Center (Nashville)

Nashville, TN · BNY Mellon

Reported status: operational

Exact location not published.

Original source · 2026-09-14

research-final:TN:d9407a5441aaa5420332
Awaiting source review

Cogent Data Center - Nashville (338 Woodycrest Ave)

Nashville, TN · Cogent Communications

Reported status: operational

Source reference: address match (exact): 338 WOODYCREST AVE, NASHVILLE, TN, 37210. Census Geocoder; not a verified facility pin.

Original source · 2026-10-10

research-final:TN:10b4b054d9812d3e35b2
Research database | Compute Equity Atlas