Review notes availableProject Azalea (Thomson Data Center Campus)
Thomson, GA · Project Turbo, LLC (developer; end user undisclosed)
Reported status: approved/permitted
Reported capacity: 400 MW planned (scope and operation unverified)
Exact location not published.
Original source · 2026-10-14
Review note: Project Azalea/Azelea spelling variation, same proposed Thomson campus unless site evidence disproves.
research-final:GA:6498dc36a5f15701da7dReview notes availableProject Azelea
Thomson, GA · Camreon Grogan; Project Turbo LLC
Reported status: proposed
Reported capacity: 400 MW (scope and operation unverified)
Approximate locality: approximate: Census 2024 Gazetteer place centroid for Thomson. Census 2024 Gazetteer centroid; not a verified facility pin.
Original source · 2026-06-15
Review note: Project Azalea/Azelea spelling variation, same proposed Thomson campus unless site evidence disproves.
research-final:GA:3fad60853b5915157820Review notes availableCleanSpark Twin City Bitcoin Mining Facility
Twin City, GA · CleanSpark, Inc.
Reported status: operational
Exact location not published.
Original source · 2026-08-05
Review note: CleanSpark Twin City Bitcoin mining, not confirmed a rentable commercial data center.
research-final:GA:95dc1b727e9e9a59de5eReview notes availableMicrosoft - Project Rita (Tyrone)
Tyrone, GA · Microsoft
Reported status: proposed
Reported capacity: 96 MW (scope and operation unverified)
Exact location not published.
Original source · 2026-06-15
Review note: Original GA1353 Microsoft - Project Rita (Tyrone) carries supplier proposed, not sufficient current primary operator/building/phase, legal source rights or evidence that the site is physically distinct and operating.
research-final:GA:8cf49cdb2d17e01d9a74Review notes availableT5 Data Centers - Georgia Campus
Undisclosed, GA · T5 Data Centers
Reported status: proposed
Reported capacity: 1.2 GW (scope and operation unverified)
Exact location not published.
Original source · 2026-06-15
Review note: Original GA1354 T5 Data Centers - Georgia Campus carries supplier proposed, not sufficient current primary operator/building/phase, legal source rights or evidence that the site is physically distinct and operating.
research-final:GA:157c0d9a3fae8bdbf443Review notes availableATL03/Red Oak
Union City, GA · TA Realty LLC, Brightstar Commercial Properties LLC
Reported status: proposed
Reported capacity: 150.00 MW (scope and operation unverified)
Exact location not published.
Original source · 2026-06-18
Review note: Original GA1355 ATL03/Red Oak carries supplier proposed, not sufficient current primary operator/building/phase, legal source rights or evidence that the site is physically distinct and operating.
research-final:GA:716bab4134b7f0dac8f3Review notes availableMicrosoft - Union City Campus
Union City, GA · Microsoft
Reported status: under construction
Reported capacity: 202 MW (scope and operation unverified)
Approximate locality: approximate: Census 2024 Gazetteer place centroid for Union City. Census 2024 Gazetteer centroid; not a verified facility pin.
Original source · 2026-06-15
Review note: Microsoft Union City and EdgeConneX/TA Realty may refer to one development partnership, distinct phases and true developer/operator require independent evidence.
research-final:GA:3a6163cba73caed61869Review notes availableThe Crossings
Union City, GA · B9 Union City Owner LLC; Link Logistics
Reported status: proposed
Approximate locality: approximate: Census 2024 Gazetteer place centroid for Union City. Census 2024 Gazetteer centroid; not a verified facility pin.
Original source · 2026-07-18
Review note: Original GA1357 The Crossings carries supplier proposed, not sufficient current primary operator/building/phase, legal source rights or evidence that the site is physically distinct and operating.
research-final:GA:c28f48229865da9ce725Review notes availableUnion City Data Center Campus (EdgeConneX / TA Realty)
Union City, GA · EdgeConneX (campus investment and operations with TA Realty; land owned by Microsoft, site development by Burr Computer Environments)
Reported status: under construction
Reported capacity: 324 MW planned (scope and operation unverified)
Exact location not published.
Original source · 2026-09-23
Review note: Microsoft Union City and EdgeConneX/TA Realty may refer to one development partnership, distinct phases and true developer/operator require independent evidence.
research-final:GA:03f67ea27b7b8f9614d3Review notes availableVantage - Stacks Rd — one-building data center with power substation (land cleared)
Union City, GA · Vantage Data Centers GA11 LLC
Reported status: under construction
Exact location not published.
Original source · 2026-08-03
Review note: Original GA1359 Vantage - Stacks Rd — one-building data center with power substation (land cleared) carries supplier under construction, not sufficient current primary operator/building/phase, legal source rights or evidence that the site is physically distinct and operating.
research-final:GA:a63353dc8a42a90ae759Review notes availableBTC Digital Vienna Mining Facility
Vienna, GA · BTC Digital Ltd.
Reported status: under construction
Reported capacity: 10 MW planned (scope and operation unverified)
Exact location not published.
Original source · 2026-10-14
Review note: BTC Digital Vienna Bitcoin mining, not a commissioned commercial data hall.
research-final:GA:3052c2ae862979ec0398Review notes availableAtlas
Villa Rica, GA
Reported status: proposed
Exact location not published.
Original source · 2026-06-18
Review note: Original GA1361 Atlas carries supplier proposed, not sufficient current primary operator/building/phase, legal source rights or evidence that the site is physically distinct and operating.
research-final:GA:a3413f598393a0c8ce0dReview notes availableAvemore Data Park
Villa Rica, GA · Atlas Development
Reported status: approved/permitted
Exact location not published.
Original source · 2026-09-23
Review note: Original GA1362 Avemore Data Park carries supplier approved/permitted, not sufficient current primary operator/building/phase, legal source rights or evidence that the site is physically distinct and operating.
research-final:GA:a07d304c5d6bda85a396Review notes availableHickman Property
Villa Rica, GA · East Village Donthan LLC
Reported status: proposed
Exact location not published.
Original source · 2026-06-18
Review note: Hickman Property originally cancelled in another location; same generic name alone is not identity proof, keep separate until parcel evidence.
research-final:GA:73c0a179a9bb93a36264Review notes availableLiberty Road Data Center Campus (EdgeConneX)
Villa Rica, GA · EdgeConneX (applicant East Village Dothan LLC)
Reported status: cancelled
Exact location not published.
Original source · 2026-09-10
Review note: Original GA1364 Liberty Road Data Center Campus (EdgeConneX) carries supplier cancelled, not sufficient current primary operator/building/phase, legal source rights or evidence that the site is physically distinct and operating.
research-final:GA:9f76978b6835c1ff6b91Review notes availableRobins Air Force Base Data Center
Warner Robins, GA
Reported status: proposed
Exact location not published.
Original source · 2026-06-18
Review note: Original GA1365 Robins Air Force Base Data Center carries supplier proposed, not sufficient current primary operator/building/phase, legal source rights or evidence that the site is physically distinct and operating.
research-final:GA:dac3de37488f58237041Review notes availableCleanSpark Washington Bitcoin Mining Facility
Washington, GA · CleanSpark, Inc.
Reported status: operational
Reported capacity: 86 MW planned; 36 MW operational (scope and operation unverified)
Exact location not published.
Original source · 2026-08-16
Review note: CleanSpark Washington Bitcoin mining, not independently a commercial colocation facility.
research-final:GA:23ad34119035333e4ed5Review notes availableSdc Atla
Winston, GA
Reported status: approved/permitted (EPA air-permit record)
Exact location not published.
Original source · 2026-10-28
Review note: Original GA1367 Sdc Atla carries supplier approved/permitted (EPA air-permit record), not sufficient current primary operator/building/phase, legal source rights or evidence that the site is physically distinct and operating.
research-final:GA:45a922c90ec2882ff3c7Review notes availableStream Atlanta West Data Center
Winston, GA · Stream Data Centers
Reported status: operational
Reported capacity: 240.00 MW (scope and operation unverified)
Exact location not published.
Original source · 2026-06-18
Review note: Stream Atlanta West existing facility versus generic Stream Data Center supplier proposal may overlap; exact address and campus needed.
research-final:GA:e1758abe853d10736886Review notes availableStream Data Center
Winston, GA
Reported status: proposed
Reported capacity: 240.00 MW (scope and operation unverified)
Exact location not published.
Original source · 2026-06-18
Review note: Stream Atlanta West existing facility versus generic Stream Data Center supplier proposal may overlap; exact address and campus needed.
research-final:GA:59eddaf8f5040cae8659Review notes availableWinston Data Center (Waldrop Farms)
Winston, GA · TC Atlanta Development
Reported status: approved/permitted
Exact location not published.
Original source · 2026-09-23
Review note: Original GA1370 Winston Data Center (Waldrop Farms) carries supplier approved/permitted, not sufficient current primary operator/building/phase, legal source rights or evidence that the site is physically distinct and operating.
research-final:GA:4de30f3417a8f5c55ca7Review notes availableCango EcoHash Georgia Facility
, GA · Cango Inc.; EcoHash Technology LLC
Reported status: operational
Reported capacity: 50 MW (scope and operation unverified)
Exact location not published.
Original source · 2026-06-15
Review note: Cango EcoHash mining/cryptocurrency-oriented infrastructure not automatically commercial data center.
research-final:GA:87cd135a66d5a14357a6Review notes availableDRFortress Acquisition and Operations
Honolulu, HI · Harrison Street; fifteenfortyseven Critical Systems Realty (1547)
Reported status: operational
Reported capacity: 4.2 MW (scope and operation unverified)
Approximate locality: approximate: Census 2024 Gazetteer county centroid for Honolulu County. Census 2024 Gazetteer centroid; not a verified facility pin.
Original source · 2026-07-18
Review note: DRFortress acquisition and operator deal may be same physical Honolulu site as original HI1373; do not create a second campus from transaction headline.
research-final:HI:472c192ff4900c214b08Review notes availableDRFortress Data Center
Honolulu, HI · DRFortress
Reported status: operational
Exact location not published.
Original source · 2026-10-21
Review note: DRFortress independent building/operator and exact address requires first-party verification, possibly same physical site as HI1372 acquisition entry.
research-final:HI:6aeeda8fa2ee8a4b24adAccepted facility identity linkedEndeavor Data Center
Honolulu, HI · Hawaiian Telcom
Reported status: operational
Exact location not published.
Original source · 2026-10-02
Review note: Exact original HI1374 accepted reviewed:hawaiiantel-endeavor-hi-20261029 from independent operator evidence; no extra physical site/map/MW. Status operational, locality/address unknown.
Read 2 source findings (2026-10-31)
Exact original HI1374 accepted reviewed:hawaiiantel-endeavor-hi-20261029 from independent operator evidence; no extra physical site/map/MW. Status operational, locality/address unknown. Evidence
Current operator confirms active Endeavor colocation on Oahu. Operator-linked specification supports the named facility but does not publish its address. No directory coordinate is promoted. Evidence
Existing project record
research-final:HI:a921370978c4147734a0Review notes availableHawaii State Data Center (Kalanimōkū Building)
Honolulu, HI · State of Hawaii Office of Enterprise Technology Services
Reported status: operational
Exact location not published.
Original source · 2026-10-21
Review note: Hawaii State Data Center inside Kalanimōkū government building may be internal government server room, not independent commercial colocation campus; valid public institution identity conditional on official site records.
research-final:HI:9327bf80586c43e89adfReview notes availableHawaiian Telcom Endeavor Data Center
Honolulu, HI · Hawaiian Telcom
Reported status: operational
Approximate locality: address match (exact): 2339 KAMEHAMEHA HWY, HONOLULU, HI, 96819. Census Geocoder; not a verified facility pin.
Original source · 2026-07-19
Review note: Current supplier name Hawaiian Telcom Endeavor matches accepted first-party canonical original HI1374; held supplier source should link to same physical operator site, not a duplicate.
research-final:HI:2577a68ee181192c0a5bReview notes availableLiberty House Data Center
Honolulu, HI
Reported status: existing (EPA facility record; status unverified)
Regulatory reference: FRS facility point (stated accuracy 30 m). EPA FRS/ECHO; not a verified facility pin.
Original source · 2026-10-28
Review note: EPA Liberty House permit does not prove separate operational data hall.
research-final:HI:d2569697036e5eca5bb1Review notes availableLumen Honolulu (550 Paiea Street)
Honolulu, HI · Lumen Technologies
Reported status: operational
Exact location not published.
Original source · 2026-10-02
Review note: Lumen Honolulu may be telecom exchange at 550 Paiea St, not assumed independently open colocation building.
research-final:HI:d3d4821575b24bc5f7e8Review notes availableServpac Puahale Data Center
Honolulu, HI · Servpac
Reported status: operational
Exact location not published.
Original source · 2026-10-02
Review note: Original Servpac Puahale has exact upstream canonical candidate; link, do not duplicate.