Snapshot: 2026-10-28. Review the linked evidence before relying on a claim. Related records and expansions must not be counted as additional facilities.
Accepted facility identity linkedIUPUI Informatics & Communications Technology Complex
Indianapolis, IN · Indiana University
Reported status: operational
Exact location not published.
Original source · 2026-06-17
Review note: Indiana University IUPUI ICTC original PeeringDB facility roots canonical reviewed:iu-indianapolis-in-20261029 at 535 W Michigan. Preserve physical academic building without new campus. Need owner validation of operation for further fields.
Read 1 source findings (2026-10-31)
Current university data-center operations page identifies its Indianapolis data center in the Informatics and Communications Technology Complex at this address. Evidence
Existing project record
research-final:IN:5ca6f23230e961e50f8eAccepted facility identity linkedLifeline Data Centers - Eastgate
Indianapolis, IN · Lifeline Data Centers
Reported status: operational
Reported capacity: 9 MW (scope and operation unverified)
Exact location not published.
Original source · 2026-07-19
Review note: Lifeline Eastgate firstparty at 401 N Shadeland Ave former mall hosts existing operating data center / emergency ops center. Exact original root accepted canonical reviewed:lifeline-eastgate-in-20261029, no second location.
Read 3 source findings (2026-10-31)
Lifeline Eastgate firstparty at 401 N Shadeland Ave former mall hosts existing operating data center / emergency ops center. Exact original root accepted canonical reviewed:lifeline-eastgate-in-20261029, no second location. Evidence
Lifeline Eastgate firstparty at 401 N Shadeland Ave former mall hosts existing operating data center / emergency ops center. Exact original root accepted canonical reviewed:lifeline-eastgate-in-20261029, no second location. Evidence
Current operator identifies its operating Eastgate data center. The whole physical campus is represented once. Evidence
Existing project record
research-final:IN:be0c774db03fc32139afReview notes availableLifeline Data Centers - Henry
Indianapolis, IN · Lifeline Data Centers
Reported status: operational
Approximate locality: address match (exact): 733 W HENRY ST, INDIANAPOLIS, IN, 46225. Census Geocoder; not a verified facility pin.
Original source · 2026-06-15
Review note: Lifeline Henry address 733 W Henry Indianapolis is numerically close to DataBank IND1 731 W Henry, may be same multitenant carrier building or legacy tenant. Don't count extra building until firstparty 733 property/site distinctness verified.
research-final:IN:83ecfa628de4ccd50e7bReview notes availableLilly Ltc-N K323 Modular Data Center Addition
Indianapolis, IN
Reported status: existing (EPA facility record; status unverified)
Exact location not published.
Original source · 2026-10-28
Review note: EPA Eli Lilly LTC-N K323 modular computer room addition at 1555 S Harding likely tenant/industrial campus module, not standalone public facility; independent physical and privacy/right checks required.
research-final:IN:8c3a65ec4f9a2591a50eReview notes availableMetrobloks Martindale-Brightwood Data Center
Indianapolis, IN · Metrobloks
Reported status: proposed
Reported capacity: 72 MW (scope and operation unverified)
Exact location not published.
Original source · 2026-06-15
Review note: Metrobloks Martindale-Brightwood Indianapolis proposal is still a development concept; no first-party completed building/campus status independently verified.
research-final:IN:5754180195394104f902Review notes availableNetrality - Indy Telcom Center - 701 W. Henry
Indianapolis, IN · Netrality Data Centers
Reported status: operational
Exact location not published.
Original source · 2026-06-17
Review note: Netrality Indy Telcom Center at 701 W Henry is a different street number from existing DataBank IND1 731 and IND2 650; verify physical operator, building and overlapping network/service tenancy before making a new standalone center.
research-final:IN:810352a5468e11d467d6Review notes availableSabey Decatur Township Data Center
Indianapolis, IN · Sabey
Reported status: proposed
Reported capacity: 250 MW (scope and operation unverified)
Exact location not published.
Original source · 2026-06-15
Review note: Sabey first-party confirms one **130-acre** proposed Decatur Township campus **6400 Kentucky Ave**, Indianapolis, 2 buildings totaling ~1m sqft, expected construction Q2 2027 and phased occupancy Q4 2029–2035. Earlier original CSV1792 same project; CSV1892 mislabeled Plainfield nearest-Census, not separate data center.
Read 1 source findings (2026-10-31)
Sabey first-party confirms one **130-acre** proposed Decatur Township campus **6400 Kentucky Ave**, Indianapolis, 2 buildings totaling ~1m sqft, expected construction Q2 2027 and phased occupancy Q4 2029–2035. Earlier original CSV1792 same project; CSV1892 mislabeled Plainfield nearest-Census, not separate data center. Evidence
research-final:IN:cb11eb9b05df2e1ad191Review notes availableUS Signal Data Center
Indianapolis, IN
Reported status: operational
Exact location not published.
Original source · 2026-06-18
Review note: US Signal acquisition of an Indianapolis facility is a distinct city/site from its Aurora IL02; verify first-party acquisition address, predecessor ownership and collision against 701 W Henry Netrality and DataBank two separate Henry sites before accepted update.
research-final:IN:feac8b7407ddb6ed8a7aReview notes availableMeta Data Center
Jeffersonville, IN · Meta Platforms, Inc.
Reported status: under construction
Reported capacity: 407.00 MW (scope and operation unverified)
Exact location not published.
Original source · 2026-06-18
Review note: Meta Jeffersonville River Ridge campus sources refer to same development (also CSV1782), distinct from Meta **Lebanon**. Meta lists Jeffersonville for 2026 Community Action Grants, which confirms local presence, **not** commissioning or number of operating halls.
research-final:IN:8b6b7969fbac1180543fReview notes availableMeta Jeffersonville Data Center
Jeffersonville, IN · Meta; Turner Construction
Reported status: under construction
Reported capacity: 225 MW (scope and operation unverified)
Exact location not published.
Original source · 2026-06-15
Review note: Meta Jeffersonville River Ridge campus sources refer to same development (also CSV1782), distinct from Meta **Lebanon**. Meta lists Jeffersonville for 2026 Community Action Grants, which confirms local presence, **not** commissioning or number of operating halls.
research-final:IN:f27b8557f5372211314cReview notes availableHenry County Technology Park
Knightstown, IN · Surge Development LLC
Reported status: approved/permitted
Exact location not published.
Original source · 2026-10-16
Review note: Surge/GM Development Henry County Technology Park near I70/SR109 at Knightstown is one proposed campus under two names, distinct from withdrawn Hancock Buck Creek project and future operator unverified.
research-final:IN:7b3ef99969773c0900f1Review notes availableSurge Development Knightstown Data Center
Knightstown, IN · Surge Development; GM Development
Reported status: proposed
Reported capacity: 1.0 GW (scope and operation unverified)
Approximate locality: approximate: Census 2024 Gazetteer place centroid for Knightstown. Census 2024 Gazetteer centroid; not a verified facility pin.
Original source · 2026-07-17
Review note: Surge/GM Development Henry County Technology Park near I70/SR109 at Knightstown is one proposed campus under two names, distinct from withdrawn Hancock Buck Creek project and future operator unverified.
research-final:IN:fa55aa27bd20b891cba3Review notes availableDigital Realty Kokomo Data Center Campus (Industrial Park North)
Kokomo, IN · Digital Realty
Reported status: proposed
Reported capacity: 1500 MW planned (scope and operation unverified)
Exact location not published.
Original source · 2026-10-16
Review note: Digital Realty Industrial Park North Kokomo ~3m sqft proposed 3 buildings on future land; neither built campus nor operating status verified by developer first-party; no 3 map pins.
research-final:IN:e5a9412cfbc07a0f3283Review notes availableLa Porte One / Project Cardinal Thomas Rose Industrial Park Data Center
La Porte, IN · La Porte One LLC
Reported status: proposed
Approximate locality: approximate: Census 2024 Gazetteer place centroid for La Porte. Census 2024 Gazetteer centroid; not a verified facility pin.
Original source · 2026-06-15
Review note: La Porte One Project Cardinal Thomas Rose Industrial Park proposal requires separate parcel/owner check, not Microsoft La Porte Radius Industrial Park, not any identically named Yorkville Project Cardinal.
research-final:IN:65dc6c432160d8281df3Review notes availableMicrosoft La Porte Data Center
La Porte, IN · Microsoft
Reported status: under construction
Reported capacity: 538 MW (scope and operation unverified)
Exact location not published.
Original source · 2026-06-15
Review note: Microsoft confirms June 18 2026 La Porte groundbreaking and July 2026 grading/site prep for **future** datacenter, 489-acre Radius Industrial Park and eventual 17-building conceptual expansion. Microsoft says vertical construction future; 2029 likely completion, NOT current operations. Two source rows one campus distinct from Microsoft Mishawaka/St Joe Farm.
Read 2 source findings (2026-10-31)
Microsoft confirms June 18 2026 La Porte groundbreaking and July 2026 grading/site prep for **future** datacenter, 489-acre Radius Industrial Park and eventual 17-building conceptual expansion. Microsoft says vertical construction future; 2029 likely completion, NOT current operations. Two source rows one campus distinct from Microsoft Mishawaka/St Joe Farm. Evidence
Microsoft confirms June 18 2026 La Porte groundbreaking and July 2026 grading/site prep for **future** datacenter, 489-acre Radius Industrial Park and eventual 17-building conceptual expansion. Microsoft says vertical construction future; 2029 likely completion, NOT current operations. Two source rows one campus distinct from Microsoft Mishawaka/St Joe Farm. Evidence
research-final:IN:f178f00cdca8830d3571Review notes availableMicrosoft La Porte First Phase Current Build
La Porte, IN · Microsoft Corporation
Reported status: under construction
Exact location not published.
Original source · 2026-06-18
Review note: Microsoft confirms June 18 2026 La Porte groundbreaking and July 2026 grading/site prep for **future** datacenter, 489-acre Radius Industrial Park and eventual 17-building conceptual expansion. Microsoft says vertical construction future; 2029 likely completion, NOT current operations. Two source rows one campus distinct from Microsoft Mishawaka/St Joe Farm.
Read 2 source findings (2026-10-31)
Microsoft confirms June 18 2026 La Porte groundbreaking and July 2026 grading/site prep for **future** datacenter, 489-acre Radius Industrial Park and eventual 17-building conceptual expansion. Microsoft says vertical construction future; 2029 likely completion, NOT current operations. Two source rows one campus distinct from Microsoft Mishawaka/St Joe Farm. Evidence
Microsoft confirms June 18 2026 La Porte groundbreaking and July 2026 grading/site prep for **future** datacenter, 489-acre Radius Industrial Park and eventual 17-building conceptual expansion. Microsoft says vertical construction future; 2029 likely completion, NOT current operations. Two source rows one campus distinct from Microsoft Mishawaka/St Joe Farm. Evidence
research-final:IN:b72e20e77e9a1ea615fdAccepted facility identity linkedWintek Corporation
Lafayette, IN · Wintek Corporation
Reported status: operational
Exact location not published.
Original source · 2025-09-26
Review note: Wintek Corporation original PeeringDB network source is the accepted root reviewed:wintek-lafayette-in-20261029, but supplier-only facility type and current operation require direct operator corroboration for further changes.
Read 1 source findings (2026-10-31)
Operator identifies its Lafayette data center and describes active client hosting and colocation; current services continue to offer colocation. Street address remains unresolved from primary sources. The Sixth Street contact address is an office, not substituted as data-center geometry. Evidence
Existing project record
research-final:IN:0f3a36b05fa4ebaf34b6Review notes availableMeta Lebanon (Project Domino)
Lebanon, IN · Meta
Reported status: under construction
Reported capacity: 1000 MW planned (scope and operation unverified)
Exact location not published.
Original source · 2026-10-22
Review note: Meta 2026 Feb company release confirms under construction and breaks ground for one **Lebanon LEAP** large campus and design 1GW **when operational**; CSV1899 Ulen nearest-Census locality actually Lebanon. Do not add four campuses or count proposed GW as energized operating MW. Distinct from Jeffersonville.
Read 1 source findings (2026-10-31)
Meta 2026 Feb company release confirms under construction and breaks ground for one **Lebanon LEAP** large campus and design 1GW **when operational**; CSV1899 Ulen nearest-Census locality actually Lebanon. Do not add four campuses or count proposed GW as energized operating MW. Distinct from Jeffersonville. Evidence
research-final:IN:6214127c58cd6215854eReview notes availableMeta Lebanon Data Center
Lebanon, IN · Meta
Reported status: under construction
Reported capacity: 1000 MW planned (scope and operation unverified)
Exact location not published.
Original source · 2026-09-23
Review note: Meta 2026 Feb company release breaks ground for one **Lebanon LEAP** large campus and design 1GW **when operational**; CSV1899 Ulen nearest-Census locality actually Lebanon. Do not add four campuses or count proposed GW as energized operating MW. Distinct from Jeffersonville.
Read 1 source findings (2026-10-31)
Meta 2026 Feb company release breaks ground for one **Lebanon LEAP** large campus and design 1GW **when operational**; CSV1899 Ulen nearest-Census locality actually Lebanon. Do not add four campuses or count proposed GW as energized operating MW. Distinct from Jeffersonville. Evidence
research-final:IN:c4f8b1f50cf62f2703bbReview notes availableMeta Lebanon LEAP District Campus
Lebanon, IN · Meta
Reported status: under construction
Reported capacity: 1.0 GW (scope and operation unverified)
Approximate locality: approximate: Census 2024 Gazetteer place centroid for Lebanon. Census 2024 Gazetteer centroid; not a verified facility pin.
Original source · 2026-06-15
Review note: Meta 2026 Feb company release breaks ground for one **Lebanon LEAP** large campus and design 1GW **when operational**; CSV1899 Ulen nearest-Census locality actually Lebanon. Do not add four campuses or count proposed GW as energized operating MW. Distinct from Jeffersonville.
Read 1 source findings (2026-10-31)
Meta 2026 Feb company release breaks ground for one **Lebanon LEAP** large campus and design 1GW **when operational**; CSV1899 Ulen nearest-Census locality actually Lebanon. Do not add four campuses or count proposed GW as energized operating MW. Distinct from Jeffersonville. Evidence
research-final:IN:f04b886335f5c14cc8d9Review notes availableOrla Llc
Lebanon, IN
Reported status: approved/permitted (EPA air-permit record)
Exact location not published.
Original source · 2026-10-28
Review note: EPA Orla LLC 3062 W SR32 Lebanon regulated data record has possible campus/corporate links but not independent proof of Meta Lebanon legal entity, physical building or operation; preserve separate until matching.
research-final:IN:df6b7568c03fef5676d6Review notes availablePrologis
Leesburg, IN
Reported status: cancelled
Exact location not published.
Original source · 2026-06-18
Review note: Prologis Kosciusko County Leesburg proposed 550-acre rezoning was **denied by planning commission April 2025**, pending any subsequent final commissioner/new petition; no operating hall or MW.
research-final:IN:d0b92b0b35966462c703Review notes availableProject Zora
Lynnville, IN · Undisclosed
Reported status: proposed
Exact location not published.
Original source · 2026-10-16
Review note: Undisclosed Project Zora in Warrick County Lynnville has no publicly confirmed operator/end user, final permits or physical data hall; hold.
research-final:IN:cbc3fa0681a9eff14c8bReview notes availableJefferson Proving Ground Data Center
Madison, IN · Undisclosed
Reported status: approved/permitted
Exact location not published.
Original source · 2026-09-21
Review note: JPG Jefferson Proving Ground Jefferson County project and JPG Data Center name refer to one potential nine-building campus; zoning appeal dispute not proof of final commissioning/operation. Keep correct county vs nearest Madison.
research-final:IN:cc3afc83b8311ddb2bf3Review notes availableJPG Data Center
Madison, IN · JPG Data Center
Reported status: proposed
Approximate locality: approximate: Census 2024 Gazetteer place centroid for Madison. Census 2024 Gazetteer centroid; not a verified facility pin.
Original source · 2026-06-15
Review note: JPG Jefferson Proving Ground Jefferson County project and JPG Data Center name refer to one potential nine-building campus; zoning appeal dispute not proof of final commissioning/operation. Keep correct county vs nearest Madison.
research-final:IN:0fb358691ca71066796eReview notes availableMarion, Indiana Bitcoin Mining Site (Bitari hosting)
Marion, IN · Undisclosed (facility owner hosting Bitari Inc.)
Reported status: operational
Reported capacity: 20 MW operational (scope and operation unverified)
Exact location not published.
Original source · 2026-10-16
Review note: Marion hosting for Bitari crypto ASIC mine has neither independently verified address nor actual facility operator; distinguish mining from general enterprise/hyperscale data center capacity.
research-final:IN:25bf2daae229b27e36ccReview notes availableProject Riverjump
Marion, IN · Undisclosed
Reported status: cancelled
Exact location not published.
Original source · 2026-10-16
Review note: Project Riverjump west Marion unnamed developer and no current permit; cannot merge with Bitari miner or call a physical operating hall.
research-final:IN:7a5e50b973921064219bReview notes availableSurge Development LLC
McCordsville, IN
Reported status: cancelled
Exact location not published.
Original source · 2026-06-18
Review note: Surge McCordsville Tuttle Orchards proposal should be checked against withdrawn Surge Buck Creek/Hancock MegaSite CSV1790/1809 by exact parcel. Similar owner/county alone not grounds for second campus or final withdrawal.
research-final:IN:55fec08a066efd9256b2Review notes availableAboutBit Merom Cryptocurrency Mining Facility
Merom, IN · AboutBit
Reported status: proposed
Reported capacity: 115 MW planned (scope and operation unverified)
Exact location not published.
Original source · 2026-09-02
Review note: AboutBit Merom coal-plant-adjacent ASIC mining has separate compute/mining taxonomy; proposed 115MW is not measured actual use, not the Fluidstack Sullivan Heartland site by name.
research-final:IN:707e5116be821562f10fReview notes availableHeartland Industrial Park (Fluidstack Sullivan County Campus)
Merom, IN · Fluidstack
Reported status: under construction
Reported capacity: 2100 MW planned (scope and operation unverified)
Exact location not published.
Original source · 2026-10-16
Review note: Fluidstack/Potentia Heartland Industrial Park Sullivan campus potential AI facility is distinct proposal from AboutBit coal-adjacent crypto miner; need current first-party operator/parcel/phase.
research-final:IN:4f85bf8b42a6755a9252