Edged Prichard Data Center
Prichard, AL · Edged Energy
Reported status: proposed
Reported capacity: 8 MW (scope and operation unverified)
Approximate locality: approximate: Census 2024 Gazetteer place centroid for Prichard. Census 2024 Gazetteer centroid; not a verified facility pin.
Original source · 2026-06-15
Read 3 source findings (2026-10-28)
Edged describes Project Gateway as a proposed 8-MW 57,000-square-foot development subject to permits, infrastructure and customer requirements; MW is project design, not energized IT load. Evidence
FOX10 quotes Edged's attorney saying the Prichard Planning Commission approved the site plan Sept 29 and construction would begin soon following moratorium dispute. It is a report of a claimed plan vote, not independently obtained signed approval, final permit disposition or commencement. Evidence
First direct reporting describes the same proposed Edged Prichard facility, before the subsequent planning/moratorium dispute; no separately identified facility from Project Gateway. Evidence