Abernathy AI data center campus (Fluidstack / TeraWulf joint venture)

This record consolidates 3 research observations while retaining source distinctions, location precision and unresolved fields.

under_constructionproject status
VERIFIED_PRIMARYbest evidence tier
3linked evidence rows
Project facts

Location and operating record

Operator / developerFluidstack (majority owner after the July 2026 sale); previously TeraWulf-managed joint venture
JurisdictionAbernathy, TX
AddressNOT_FOUND
Location precisionstreet address
CoordinatesNot published; no coordinate inferred
CapacityNot established
AliasesAbernathy AI data center campus (Fluidstack / TeraWulf joint venture) · Abernathy campus
Evidence coverage

What has been researched

Project profile0 rows
Intent / permits0 rows
Civic / infrastructure0 rows
SOURCE RECORD

Abernathy AI data center campus (Fluidstack / TeraWulf joint venture): source record

under_construction

Distinct from Aligned's Project Caprock, which is also near Abernathy in Hale County - do not conflate. Cleanview reports an operational date of 2027 while TeraWulf targeted H2 2026 delivery; the lease term was described as potentially shortening from 25 to 20 or 15 years.

Key data: NOT_FOUND - the project is described as able to leverage existing transmission infrastructure | NOT_FOUND - Hale County is in SPS/Xcel (SPP) territory; the specific interconnection was not confirmed | NOT_FOUND | NOT_FOUND

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1

Sources

Evidence and provenance

Open TX state research →

Abernathy AI data center campus (Fluidstack / TeraWulf joint venture) Data Center Project | Abernathy | Compute Equity Atlas