approved
Investment conflict: $10 billion (June 2026 announcement) vs an earlier '$8.5 billion minimum' figure (missouridatacenters.org). Building conflict: up to 17 buildings (missouridatacenters.org) vs an initial 8 buildings plus expansion (datacentermap). Jobs conflict: 400 permanent/direct jobs plus thousands of trade jobs (June 2026 reporting) vs approximately 150 jobs at $85,000 average in the December 2025 abatement framework. servercountry.org lists 1,300 MW; no MW figure appears in the primary announcements, so none is asserted.
Key data: Ameren Missouri | MISO (Ameren Missouri / AMMO)
Claim classification: Not yet assigned
Status date: 2026-09-13