Compute Equity Atlas
← National map
Source-backed project record · TX

Amazon Round Rock data center (PUD-153)

This record consolidates 7 research observations while retaining source distinctions, location precision and unresolved fields.

approved_or_permittedproject status
VERIFIED_PRIMARYbest evidence tier
7linked evidence rows
Project facts

Location and operating record

Operator / developerNOT_FOUND (Amazon-linked per city announcement)
JurisdictionRound Rock, TX
AddressAlong County Road 172 and McNeil Road, north of SH 45
Location precisionparcel or bounded site
CoordinatesNot published; no coordinate inferred
CapacityNot established
AliasesAmazon Round Rock data center (PUD-153) · CR 172 / McNeil Road PUD · PUD 153 · Ordinance O-2024-008 · Amazon Round Rock project
Evidence coverage

What has been researched

Project profile0 rows
Intent / permits0 rows
Civic / infrastructure1 rows
SOURCE RECORD

Amazon Round Rock data center (PUD-153): source record

approved

The zoning application originally covered ~193 acres and was reduced to ~149 acres. The city's own release names the Amazon project; no operating entity or LLC propco name was located.

Key data: NOT_FOUND | ERCOT South Central / Austin-Central Texas load zone | NOT_FOUND | PUD-153 / Ordinance O-2024-008

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

OWNERSHIP AND PROFILE

Amazon Round Rock data center (PUD-153): ownership and profile

approved

Developer: Amazon (as identified in the City of Round Rock announcement) | Permit applicant: Applicant for PUD-153 rezoning | County: Williamson | Research region: Austin / Central Texas | Tenants/customers: Amazon

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

POWER AND GRID

Amazon Round Rock data center (PUD-153): power and grid

approved

Key data: Utility region: ERCOT | Grid area: ERCOT South Central / Austin-Central Texas load zone

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

WATER AND COOLING

Amazon Round Rock data center (PUD-153): water and cooling

approved

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

PERMITS AND JURISDICTION

Amazon Round Rock data center (PUD-153): permits and jurisdiction

approved

Key data: Zoning case: PUD-153 / Ordinance O-2024-008 | Permit IDs: Round Rock Ordinance O-2024-008 (PUD-153) | Jurisdictions: City of Round Rock | Williamson County | ERCOT

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

CIVIC AND COMMUNITY

Amazon Round Rock data center (PUD-153): civic and community

approved

Rezoning drew public attention; the city published a dedicated news release and later a standing data center information page

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

TIMELINE

Amazon Round Rock data center (PUD-153): timeline

approved

Round Rock City Council unanimously approves PUD-153 zoning (Ordinance O-2024-008) allowing data center use on the CR 172 / McNeil Rd site

Claim classification: Not yet assigned

Status date: 2024-01-11

Open source 1 →

Sources

Evidence and provenance

Open TX state research →

Amazon Round Rock data center (PUD-153) Data Center Project | Round Rock | Compute Equity Atlas