Applied Digital Delta Forge 1

This record consolidates 15 research observations while retaining source distinctions, location precision and unresolved fields.

proposed_or_reviewproject status
VERIFIED_PRIMARYbest evidence tier
15linked evidence rows
Project facts

Location and operating record

Operator / developerApplied Digital Corporation
JurisdictionBoyce, LA
AddressJames Rd & LA-121 (site vicinity per Data Center Map); England Economic & Industrial Development District
Location precisionlocality centroid
CoordinatesNot published; no coordinate inferred
Capacity430 MW
AliasesApplied Digital Delta Forge 1 · Delta Forge campus, England Airpark · Delta Forge · APLD Rapides Parish AI factory · Applied Digital Central Louisiana campus
Evidence coverage

What has been researched

Project profile0 rows
Intent / permits0 rows
Civic / infrastructure0 rows
SOURCE RECORD

Applied Digital Delta Forge 1: source record

planned

430 MW is total utility power and 300 MW is critical IT load per the company's own release; the 756 MW figure is Cleco generation capacity and is NOT IT load. Acreage conflicts: ~300 acres (LED) vs >500 acres (company release) vs ~672 acres (Data Center Map 'Project Lightning' listing). Investment conflicts: $3.6B (LED) vs 'now-$7 billion' / $7.2B PILOT framing in local reporting.

Key data: Cleco Power LLC

Claim classification: Not yet assigned

Status date: 2026-09

Open source 1 →

OWNERSHIP AND PROFILE

Applied Digital Delta Forge 1: ownership and profile

planned

Developer: Applied Digital Corporation | Permit applicant: APLD ALX-1 LLC (entity named on Data Center Map listing for the Boyce site) | County: Rapides Parish | Research region: Central Louisiana | Tenants/customers: Unnamed U.S.-based investment-grade hyperscaler (15-year lease, 300 MW critical IT, ~$7.5B contracted value)

Claim classification: Not yet assigned

Status date: 2026-09

Open source 1 →

under construction

Applied Digital announced a 15-year lease for 300 MW of critical IT capacity with an unnamed U.S.-based investment-grade hyperscaler, approximately $7.5B of contracted value.

Key data: 15-yr lease; ~$7.5B contracted value

Claim classification: documented_fact · Verification: verified · Retrieved: 2026-09-13

Status date: 2026-04-23

Limitation: Tenant not named.

Open source 1 →

POWER AND GRID

Applied Digital Delta Forge 1: power and grid

planned

Key data: Utility: Cleco Power LLC | Gross MW: 430 | IT load MW: 300

Claim classification: Not yet assigned

Status date: 2026-09

Open source 1 →

under construction

Cleco announced it will power the data center planned for Rapides Parish; trade reporting describes a 756 MW natural gas plant Cleco will construct to serve the campus.

Key data: 756 MW gas plant (generation)

Claim classification: documented_fact · Verification: verified · Retrieved: 2026-09-13

Status date: 2026-05-26

Limitation: 756 MW is generation capacity, not IT load.

Open source 1 →

WATER AND COOLING

Applied Digital Delta Forge 1: water and cooling

planned

Key data: Cooling: Closed-loop / waterless cooling per LED announcement

Claim classification: Not yet assigned

Status date: 2026-09

Open source 1 →

PERMITS AND JURISDICTION

Applied Digital Delta Forge 1: permits and jurisdiction

planned

Key data: Jurisdictions: England Economic & Industrial Development District | Rapides Parish | State of Louisiana | Tax incentives: Act 730 data center sales-and-use tax exemption | PILOT term sheet approved by England Authority in April 2026

Claim classification: Not yet assigned

Status date: 2026-09

Open source 1 →

under construction

The England Economic & Industrial Development District approved PILOT term sheet terms for the Applied Digital project, described in local coverage as a now-$7 billion / $7.2 billion project.

Key data: PILOT terms approved

Claim classification: documented_fact · Verification: partially_verified · Retrieved: 2026-09-13

Status date: 2026-04-27

Limitation: Video item; term sheet document not retrieved.

Open source 1 →

ENVIRONMENT AND SITE

Applied Digital Delta Forge 1: environment and site

planned

Key data: Surrounding infrastructure: Cleco plans a 756 MW natural gas plant to serve the campus (DataCenterDynamics)

Claim classification: Not yet assigned

Status date: 2026-09

Open source 1 →

TIMELINE

Applied Digital Delta Forge 1: timeline

planned

Applied Digital breaks ground on Delta Forge 1 (430 MW total utility power, up to 300 MW critical IT)

Claim classification: Not yet assigned

Status date: 2026-01-22

Open source 1 →

planned

Applied Digital announces 15-year, 300 MW critical IT lease with a U.S. investment-grade hyperscaler

Claim classification: Not yet assigned

Status date: 2026-04-23

Open source 1 →

planned

England Authority approves PILOT terms for the project

Claim classification: Not yet assigned

Status date: 2026-04-27

Open source 1 →

planned

Cleco announces it will power the Rapides Parish data center

Claim classification: Not yet assigned

Status date: 2026-05-26

Open source 1 →

STATUS AND DEVELOPMENT

Applied Digital Delta Forge 1: status and development

under construction

Applied Digital broke ground on Delta Forge 1, described as a 430 MW AI factory campus with up to 300 MW of critical IT load across two 150 MW facilities on more than 500 acres, with initial operations expected mid-2027.

Key data: 430 MW total; 300 MW critical IT

Claim classification: documented_fact · Verification: verified · Retrieved: 2026-09-13

Status date: 2026-01-22

Limitation: Company release.

Open source 1 →

ECONOMIC AND TAX

Applied Digital Delta Forge 1: economic and tax

announced

LED announced the $3.6 billion Applied Digital AI factory campus in Rapides Parish/Boyce with 200 direct jobs at 150% of the state average wage, more than 1,000 construction jobs, Cleco power and closed-loop waterless cooling.

Key data: $3.6B; 200 direct jobs

Claim classification: proposal_or_announced_commitment · Verification: verified · Retrieved: 2026-09-13

Status date: 2025-12

Limitation: Investment figure conflicts with later $7B/$7.2B PILOT framing.

Open source 1 →