Source-backed project record · GA

ATL2 LLC / Serverfarm

This canonical record consolidates 4 source-backed observations without discarding aliases, limitations or unresolved dimensions.

under_constructionproject status
VERIFIED_PRIMARYbest evidence tier
4linked evidence rows
Project facts

Location and operating record

Operator / developerNot established in current evidence
JurisdictionNewton County / Covington, GA
Address10835 Hazelbrand Rd NE, Covington, GA 30014, Newton County
Location precisionstreet address
Coordinatesnull, null
Capacity90 MW
AliasesATL2 LLC / Serverfarm · ATL2 LLC / Serverfarm (permit 29898)
Evidence coverage

What has been researched

Project profile3 rows
Intent / permits0 rows
Civic / infrastructure1 rows
EXACT LOCATION and OWNERSHIP CHAIN

ATL2 LLC / Serverfarm: exact location and ownership chain

VERIFIED_PRIMARY

The EPD draft permit gives address, AIRS number, permit number, application date and the applicant's mailing address

Key data: 10835 Hazelbrand Rd NE, Covington, GA 30014, Newton County; AIRS 04-13-217-00079; permit 7374-217-0079-S-01-0; Application No. 29898 dated 2025-10-03; mailing address 155 NE 100th St Ste 302, Seattle WA

Limitation: The Seattle mailing address does not match Serverfarm's corporate base; the ATL2 LLC-to-Serverfarm relationship is asserted by secondary sources, not by the permit

Open source →

POWER SUPPLIER

ATL2 LLC / Serverfarm: power supplier

CORROBORATED

The site is designed around an adjacent on-site gas generation plant rather than grid supply from the incumbent utility

Key data: Adjacent VoltaGrid on-site gas plant of approximately 90 MW, not Georgia Power grid supply; 37 diesel backup generators

Limitation: No interconnection or power purchase agreement reference; an EPD Notice of Violation dated 2026-07-02 is noted by the same source

Open source →

PLANNING ZONING CONTACT (state)

ATL2 LLC / Serverfarm: planning zoning contact (state)

VERIFIED_PRIMARY

The EPD draft permit names the assigned state engineer for the application

Key data: Mr. Sean Taylor, Georgia EPD

Limitation: Direct phone and email for the named engineer were not captured

Open source →

UTILITY INTERCONNECTION QUEUE

ATL2 LLC / Serverfarm: utility interconnection queue

Draft permit; NOVs issued

EPD's narrative documents the backup fleet (37 diesel generators: 36 × 3.3 MW plus one 2.25 MW administrative unit; sources G01–G36 at 32.1 MMBtu/hr each) but states **no facility MW load, no interconnection details, and no queue position**. Separately, EPD issued notices of violation to **VoltaGrid and Serverfarm** over a 33-engine "pop-up" prime-power plant in Covington that environmental groups said was under construction without permits — the first of its kind in Georgia.

Key data: 37 generators (36 × 3.3 MW + 1 × 2.25 MW); 33-engine adjacent power plant; NOVs issued; grid load n.a.

Status date: 2026-07-09 (NOV coverage)

Limitation: The NOV documents themselves were not obtained; no permit/case number for the NOVs is published in the coverage. (confidence detail: VERIFIED_PRIMARY (EPD) / CORROBORATED (NOV))

Open source →

Sources

Evidence and provenance

  • Georgia Environmental Protection Division · VERIFIED PRIMARY
    Limitation: The Seattle mailing address does not match Serverfarm's corporate base; the ATL2 LLC-to-Serverfarm relationship is asserted by secondary sources, not by the permit
  • Compute Atlas · CORROBORATED
    Limitation: No interconnection or power purchase agreement reference; an EPD Notice of Violation dated 2026-07-02 is noted by the same source
  • Georgia EPD; Metro Atlanta CEO · VERIFIED PRIMARY
    Limitation: The NOV documents themselves were not obtained; no permit/case number for the NOVs is published in the coverage. (confidence detail: VERIFIED_PRIMARY (EPD) / CORROBORATED (NOV))

Open GA state research →