Cassini Gateway I Data Center Campus

This record consolidates 16 research observations while retaining source distinctions, location precision and unresolved fields.

proposed_or_reviewproject status
CORROBORATEDbest evidence tier
16linked evidence rows
Project facts

Location and operating record

Operator / developerNOT_FOUND
JurisdictionSherman, TX
AddressNOT_FOUND
Location precisionparcel or bounded site
CoordinatesNot published; no coordinate inferred
CapacityNot established
AliasesCassini Gateway I Data Center Campus · Progress Park I · Cassini Gateway · Cassini Gateway I
Evidence coverage

What has been researched

Project profile0 rows
Intent / permits0 rows
Civic / infrastructure0 rows
SOURCE RECORD

Cassini Gateway I Data Center Campus: source record

announced

Announced in 2017; no source fetched this session confirms construction, completion, or cancellation, so status remains 'announced' with an unresolved current-status gap. Sources conflict slightly on park size (3,000 vs 3,300 acres). Sherman's later semiconductor investment (Texas Instruments, GlobiTech/GlobalWafers, Coherent) is adjacent context, not part of this campus.

Key data: NOT_FOUND | ERCOT | City of Sherman municipal water and municipal sewer; site has access to an industrial-scale water line | NOT_FOUND

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

OWNERSHIP AND PROFILE

Cassini Gateway I Data Center Campus: ownership and profile

announced

Developer: Thea Development, LLC (CEO Margie Guido) | Owner: Thea Development, LLC purchased the land from the Sherman Economic Development Corporation (SEDCO) | County: Grayson | Research region: Temple-Killeen-Waco / Bryan-College Station / Texoma

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

POWER AND GRID

Cassini Gateway I Data Center Campus: power and grid

announced

Key data: Utility region: ERCOT North | Grid area: ERCOT | Substations: A 'very large' new substation was planned for the campus (Data Center Dynamics) | Transmission: Site has access to high-voltage electric transmission lines and natural gas transmission lines

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

WATER AND COOLING

Cassini Gateway I Data Center Campus: water and cooling

announced

Key data: Water utility: City of Sherman municipal water and municipal sewer; site has access to an industrial-scale water line | Water source: Municipal supply; Sherman water capacity cited as 45 million gallons per day | Wastewater: Municipal sewage service available at the site

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

PERMITS AND JURISDICTION

Cassini Gateway I Data Center Campus: permits and jurisdiction

announced

Key data: Jurisdictions: State of Texas | Grayson County | City of Sherman | Sherman Economic Development Corporation | ERCOT

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

ENVIRONMENT AND SITE

Cassini Gateway I Data Center Campus: environment and site

announced

Key data: Surrounding infrastructure: Adjacent to the 758 MW Panda Sherman natural-gas cogeneration power plant (commissioned 2014)

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

announced

Key data: Surrounding infrastructure: Located 60 miles north of Dallas within Progress Park I industrial park

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

announced

Key data: Surrounding infrastructure: Existing concrete road network inside the park

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

TIMELINE

Cassini Gateway I Data Center Campus: timeline

announced

SEDCO and Thea Development announce Cassini Gateway I Data Center Campus

Claim classification: Not yet assigned

Status date: 2017-06-02

Open source 1 →

announced

Plan announced to build one data center per year for five years at about $200 million each

Claim classification: Not yet assigned

Status date: 2017

Open source 1 →

DEVELOPER

Cassini Gateway I Data Center Campus: developer

announced

SEDCO and Thea Development, LLC announced the Cassini Gateway I Data Center Campus at Progress Park I in Sherman; Thea Development's CEO is Margie Guido and SEDCO's president is John Plotnik.

Key data: Developer: Thea Development, LLC; land seller: SEDCO

Claim classification: REPORTED_FACT · Verification: CORROBORATED_MULTI_SOURCE · Retrieved: 2026-09-05

Status date: 2017-06-02

Open source 1 →

BUILDING SQFT

Cassini Gateway I Data Center Campus: building sqft

announced

The announced campus was designed to accommodate more than 1 million square feet of data center space with more than $1 billion in capital investment.

Key data: >1,000,000 sq ft; >$1B investment

Claim classification: REPORTED_FACT · Verification: CORROBORATED_MULTI_SOURCE · Retrieved: 2026-09-05

Status date: 2017-06-02

Open source 1 →

CAMPUS ACRES

Cassini Gateway I Data Center Campus: campus acres

announced

Thea Development agreed to pay approximately $1.84 million for an initial 48 acres inside Progress Park I, described as a 3,000-acre industrial park, and planned one data center every 12 months for five years at about $200 million each.

Key data: 48 acres initial purchase for ~$1.84M; ~$200M per building

Claim classification: REPORTED_FACT · Verification: VERIFIED_SINGLE_SOURCE · Retrieved: 2026-09-05

Limitation: Acreage and park size differ between sources (3,000 vs 3,300 acres); no post-2017 status confirmation was located.

Open source 1 →

SUBSTATION

Cassini Gateway I Data Center Campus: substation

announced

Reporting on the campus states a 'very large' substation was planned, with the site already served by high-voltage electric lines and natural gas transmission lines.

Key data: New 'very large' substation planned

Claim classification: REPORTED_FACT · Verification: VERIFIED_SINGLE_SOURCE · Retrieved: 2026-09-05

Open source 1 →

SURROUNDING INFRASTRUCTURE

Cassini Gateway I Data Center Campus: surrounding infrastructure

announced

The campus site is adjacent to the 758 MW Panda Sherman gas-fired cogeneration plant, has access to an industrial-scale water line, municipal water and sewer, and Sherman water capacity was cited at 45 million gallons per day.

Key data: Adjacent 758 MW Panda Sherman plant; 45 MGD municipal water capacity

Claim classification: REPORTED_FACT · Verification: CORROBORATED_MULTI_SOURCE · Retrieved: 2026-09-05

Status date: 2017-06-02

Open source 1 →

JOBS

Cassini Gateway I Data Center Campus: jobs

announced

The announcement projected more than 150 direct jobs and 350 construction jobs over five years for the Sherman campus.

Key data: >150 direct jobs; 350 construction jobs over 5 years

Claim classification: REPORTED_FACT · Verification: CORROBORATED_MULTI_SOURCE · Retrieved: 2026-09-05

Status date: 2017-06-02

Open source 1 →