Source-backed project record · TX

Cipher Black Pearl Data Center

This record consolidates 16 research observations while retaining source distinctions, location precision and unresolved fields.

operationalproject status
VERIFIED_PRIMARYbest evidence tier
16linked evidence rows
Project facts

Location and operating record

Operator / developerAmazon Data Services, Inc. (registered operator as of 2026); Cipher Digital (site developer)
JurisdictionWink, TX
Address11786 Co Rd 209, Wink, TX
Location precisionstreet address
CoordinatesNot published; no coordinate inferred
Capacity300 MW
AliasesCipher Black Pearl Data Center · Black Pearl · Cipher Black Pearl · Black Pearl Data Center
Evidence coverage

What has been researched

Project profile0 rows
Intent / permits0 rows
Civic / infrastructure0 rows
SOURCE RECORD

Cipher Black Pearl Data Center: source record

operational

Best-documented crypto-to-AI conversion in the region: a bitcoin mining site that re-registered in January 2026 with Amazon Data Services, Inc. as both occupant and operator. TDLR contact of record: Chris Totin. Design firm/architect not recorded.

Key data: ERCOT

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

OWNERSHIP AND PROFILE

Cipher Black Pearl Data Center: ownership and profile

operational

Developer: Cipher Mining / Cipher Digital | Owner: Cipher Black Pearl LLC | Property entity: Cipher Black Pearl LLC | Permit applicant: Cipher Black Pearl LLC (TDLR project registration) | County: Winkler | Research region: Abilene-West Central Texas / Midland-Odessa-Permian Basin | Tenants/customers: Amazon Data Services, Inc. (registered occupant as of 2026-01-23)

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

POWER AND GRID

Cipher Black Pearl Data Center: power and grid

operational

Key data: Utility region: ERCOT West | Grid area: ERCOT | Gross MW: 300 | Requested load MW: 300 | Grid/market records: Conditional interconnection approval reported up to 300 MW; phase 1 up to 150 MW (per company 10-K reporting, not verified in this session)

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

WATER AND COOLING

Cipher Black Pearl Data Center: water and cooling

operational

Key data: Cooling: 250 MW air-cooled plus 50 MW liquid-cooled

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

PERMITS AND JURISDICTION

Cipher Black Pearl Data Center: permits and jurisdiction

operational

Key data: Permit IDs: TDLR TABS2025001763 | Jurisdictions: Winkler County | Texas Department of Licensing and Regulation | Texas Comptroller of Public Accounts | ERCOT | Tax incentives: [object Object],[object Object] | {"agreement_name":"Texas Comptroller Qualifying Data Center Project registration - Cipher Black Pearl LLC Data Center","agreement_number":"DC470713-OW1 / DC470713-OC1 / DC470713-OP1","approval_date":"2024-02-15","estimated_value":"State sales-and-use tax exemption","government_entity":"Texas Comptroller of Public Accounts","investment_commitment":"NOT_FOUND","jobs_commitment":"NOT_FOUND","source_url":"https://comptroller.texas.gov/taxes/data-centers/data-center-lists.php","term":"Exemption end date 2026-01-22"} | {"agreement_name":"Texas Comptroller Qualifying LARGE Data Center Project registration - Cipher Black Pearl LLC Data Center","agreement_number":"LD089477-OW1 / LD089477-OC1 / LD089477-OP1","approval_date":"2026-01-23","estimated_value":"State sales-and-use tax exemption","government_entity":"Texas Comptroller of Public Accounts","investment_commitment":"NOT_FOUND","jobs_commitment":"NOT_FOUND","source_url":"https://comptroller.texas.gov/taxes/data-centers/data-center-lists.php","term":"NOT_FOUND"}

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

TIMELINE

Cipher Black Pearl Data Center: timeline

operational

Cipher acquires the Black Pearl site

Claim classification: Not yet assigned

Status date: 2023 (late)

Open source 1 →

operational

TDLR construction registration: start 2024-08-07, completion 2024-12-31, $7,000,000, 19,579 sq ft; owner Cipher Black Pearl LLC, 1 Vanderbilt Ave 54th Floor, New York NY 10017

Claim classification: Not yet assigned

Status date: 2024-09-25

Open source 1 →

operational

Registered as a Qualifying Data Center Project with the Texas Comptroller

Claim classification: Not yet assigned

Status date: 2024-02-15

Open source 1 →

operational

Target energization Q2 2025

Claim classification: Not yet assigned

Status date: 2025-Q2

Open source 1 →

operational

Small-project exemption ends and the site re-registers as a Qualifying LARGE Data Center Project with Amazon Data Services, Inc. as occupant and operator

Claim classification: Not yet assigned

Status date: 2026-01-23

Open source 1 →

operational

TDLR project status recorded as Inspection Complete

Claim classification: Not yet assigned

Open source 1 →

STREET ADDRESS

Cipher Black Pearl Data Center: street address

operational

The TDLR construction registration TABS2025001763 places the Black Pearl Data Center at 11786 Co Rd 209, Wink TX 79789 in Winkler County, with Cipher Black Pearl LLC of 1 Vanderbilt Ave, 54th Floor, New York NY 10017 as owner and Chris Totin as contact.

Key data: 11786 Co Rd 209, Wink TX 79789; owner Cipher Black Pearl LLC

Claim classification: SOURCED_FACT · Verification: VERIFIED · Retrieved: 2026-09-05

Status date: 2024-09-25

Open source 1 →

BUILDING SQFT

Cipher Black Pearl Data Center: building sqft

operational

The TDLR filing records a 19,579 sq ft single-story pre-engineered metal building at a registered cost of $7,000,000, with construction from 7 August 2024 to 31 December 2024 and a project status of Inspection Complete.

Key data: 19,579 sq ft; $7,000,000; Inspection Complete

Claim classification: SOURCED_FACT · Verification: VERIFIED · Retrieved: 2026-09-05

Status date: 2024-09-25

Open source 1 →

CAPACITY GROSS POWER

Cipher Black Pearl Data Center: capacity gross power

operational

Cipher Mining's Black Pearl site was announced at 300 MW, split as 250 MW air-cooled and 50 MW liquid-cooled, with the site acquired in late 2023 and energization targeted for Q2 2025.

Key data: 300 MW (250 MW air-cooled + 50 MW liquid-cooled)

Claim classification: SOURCED_FACT · Verification: VERIFIED · Retrieved: 2026-09-05

Open source 1 →

TENANT CUSTOMER

Cipher Black Pearl Data Center: tenant customer

operational

The Comptroller registry shows the small-project exemption for Cipher Black Pearl LLC ending 22 January 2026 and the site re-registering the next day as a Qualifying Large Data Center Project with Amazon Data Services, Inc. as both occupant and operator.

Key data: DC470713 ends 2026-01-22; LD089477 effective 2026-01-23 with Amazon Data Services

Claim classification: SOURCED_FACT · Verification: VERIFIED · Retrieved: 2026-09-05

Status date: 2026-01-23

Open source 1 →

PROJECT STATUS

Cipher Black Pearl Data Center: project status

operational

The transition of the registered occupant and operator from Cipher Black Pearl LLC to Amazon Data Services, Inc. in January 2026 is the clearest documented crypto-mining-to-AI/hyperscale conversion in the study region.

Key data: Occupant/operator change from Cipher to Amazon Data Services

Claim classification: INFERENCE · Verification: VERIFIED · Retrieved: 2026-09-05

Status date: 2026-01-23

Limitation: The registry records a change in registered roles; it does not itself state that the workload changed from mining to AI.

Open source 1 →

Sources

Evidence and provenance

Open TX state research →