operational
Buildings addressed at 300 Houston School Road and 481, 500, 540 and 581 Austin Boulevard.
Key data: Oncor Electric Delivery (assumed) | ERCOT
Claim classification: Not yet assigned
Status date: 2026-09-05
This record consolidates 9 research observations while retaining source distinctions, location precision and unresolved fields.
| Operator / developer | Compass Datacenters |
|---|---|
| Jurisdiction | Red Oak, TX |
| Address | 300 Houston School Road |
| Location precision | street address |
| Coordinates | Not published; no coordinate inferred |
| Capacity | Not established |
| Aliases | Compass Datacenters Red Oak Campus (Houston School Road) · Red Oak Campus |
| Project profile | 0 rows |
|---|---|
| Intent / permits | 0 rows |
| Civic / infrastructure | 0 rows |
Buildings addressed at 300 Houston School Road and 481, 500, 540 and 581 Austin Boulevard.
Key data: Oncor Electric Delivery (assumed) | ERCOT
Claim classification: Not yet assigned
Status date: 2026-09-05
Developer: Compass Datacenters | Owner: Compass Datacenters | County: Ellis | Research region: Dallas-Fort Worth / North Texas
Claim classification: Not yet assigned
Status date: 2026-09-05
Key data: Utility: Oncor Electric Delivery (assumed) | Grid area: ERCOT
Claim classification: Not yet assigned
Status date: 2026-09-05
Claim classification: Not yet assigned
Status date: 2026-09-05
Key data: Permit IDs: TDLR filing for Roadrunner Building 2 (2022) | Jurisdictions: City of Red Oak | Ellis County | TDLR | ERCOT
Claim classification: Not yet assigned
Status date: 2026-09-05
Campus established at 165 acres
Claim classification: Not yet assigned
Status date: 2019
Campus expanded to 225 acres
Claim classification: Not yet assigned
Status date: 2020
Roadrunner Building 2 filed at 481 Austin Blvd, 250,000 sq ft, $100M
Claim classification: Not yet assigned
Status date: 2022
Three additional buildings at 500, 540 and 581 Austin Boulevard targeted completion
Claim classification: Not yet assigned
Status date: 2025/2026