CRG Festus Data Center

This record consolidates 15 research observations while retaining source distinctions, location precision and unresolved fields.

approved_or_permittedproject status
CORROBORATEDbest evidence tier
15linked evidence rows
Project facts

Location and operating record

Operator / developerCRG (a Clayco company)
JurisdictionFestus, MO
AddressNorth of Highway 67 and west of Highway CC (Old England Rd and US-67)
Location precisionparcel or bounded site
CoordinatesNot published; no coordinate inferred
CapacityNot established
AliasesCRG Festus Data Center · Festus data center campus
Evidence coverage

What has been researched

Project profile0 rows
Intent / permits0 rows
Civic / infrastructure5 rows
SOURCE RECORD

CRG Festus Data Center: source record

approved

Acreage conflict: roughly 360 acres (project site / missouridatacenters.org) vs a '240-acre campus' described by datacentermap; an unofficial LinkedIn analysis circulated figures of about 674 acres, 902 MW and four buildings that are speculative and not used. servercountry.org lists 1,000 MW; no MW value is asserted. CRG leadership named: Chris McKee (president), Rohit Kinra (SVP Data Centers), Bob Clark (Clayco executive chairman). City consultant MarksNelson Advisors LLC (Steve Etcher) engaged under Ordinance 4875. End user/operator not disclosed. An Ameren large data center rate was before the Missouri PSC during the approval process.

Key data: Ameren Missouri | MISO (Ameren Missouri / AMMO) | Bill No. 4876 (rezoning)

Claim classification: Not yet assigned

Status date: 2026-09-13

Open source 1

OWNERSHIP AND PROFILE

CRG Festus Data Center: ownership and profile

approved

Developer: CRG (a Clayco company) | County: Jefferson | Research region: St. Louis south / Jefferson County

Claim classification: Not yet assigned

Status date: 2026-09-13

Open source 1

POWER AND GRID

CRG Festus Data Center: power and grid

approved

Key data: Utility: Ameren Missouri | Grid area: MISO (Ameren Missouri / AMMO)

Claim classification: Not yet assigned

Status date: 2026-09-13

Open source 1

WATER AND COOLING

CRG Festus Data Center: water and cooling

approved

Claim classification: Not yet assigned

Status date: 2026-09-13

Open source 1

PERMITS AND JURISDICTION

CRG Festus Data Center: permits and jurisdiction

approved

Key data: Zoning case: Bill No. 4876 (rezoning) | Jurisdictions: Festus | Jefferson County | Missouri | Tax incentives: No real property tax abatement; partial personal property abatement sought | $1.3 billion in taxes and community benefits over 25 years projected | Approximately $25 million per year to the City of Festus

Claim classification: Not yet assigned

Status date: 2026-09-13

Open source 1

CIVIC AND COMMUNITY

CRG Festus Data Center: civic and community

approved

$45 million in direct community benefit over 10 years

Claim classification: Not yet assigned

Status date: 2026-09-13

Open source 1

approved

Up to $5 million for a firehouse

Claim classification: Not yet assigned

Status date: 2026-09-13

Open source 1

approved

Lawsuit filed 2026-04-08 by Wake Up JeffCo and four property owners

Claim classification: Not yet assigned

Status date: 2026-09-13

Open source 1

approved

All four incumbent council members were ousted in the April 2026 municipal election

Claim classification: Not yet assigned

Status date: 2026-09-13

Open source 1

approved

Festus City Council approved the rezoning 6-2 in November 2025 and the development agreement 6-2 on 2026-03-30; Wake Up JeffCo and four property owners sued on 2026-04-08 and all four incumbent council members were ousted in the April 2026 municipal election.

Key data: Two 6-2 approvals; lawsuit 2026-04-08; four incumbents ousted

Claim classification: documented_fact · Verification: source_backed_unverified · Retrieved: 2026-09-13

Status date: 2026-04-08

Limitation: Advocacy-run tracker; council vote records were not obtained directly from city minutes.

Open source 1

TIMELINE

CRG Festus Data Center: timeline

approved

Festus City Council approved rezoning 6-2 (Bill No. 4876)

Claim classification: Not yet assigned

Status date: 2025-11

Open source 1

approved

Festus City Council approved the development agreement 6-2

Claim classification: Not yet assigned

Status date: 2026-03-30

Open source 1

approved

Wake Up JeffCo and four property owners filed suit

Claim classification: Not yet assigned

Status date: 2026-04-08

Open source 1

ECONOMIC AND TAX

CRG Festus Data Center: economic and tax

approved

The Festus data center project is described as a $6 billion development generating $1.3 billion in taxes and community benefits over 25 years, roughly $25 million per year to the City of Festus, $45 million in direct community benefit over 10 years and up to $5 million for a firehouse, with no real property tax abatement and only a partial personal property abatement sought.

Key data: $6B investment; ~$25M/yr to Festus; no real property abatement

Claim classification: official_estimate_or_forecast · Verification: source_backed_unverified · Retrieved: 2026-09-13

Status date: 2026-03-30

Limitation: Developer-published projections, not audited or independently modeled figures.

Open source 1

LOCATION AND SITE

CRG Festus Data Center: location and site

CONFLICTING

Datacentermap lists a CRG Festus campus at Old England Rd and US-67 in Festus described as a 240-acre campus with potential investment above $1 billion, while the project's own materials describe roughly 360 acres north of Highway 67 west of Highway CC.

Key data: 240-acre campus per directory vs ~360 acres per project

Claim classification: documented_fact · Verification: conflicting_sources_preserved · Retrieved: 2026-09-13

Limitation: Acreage and investment figures conflict between the directory and the project's own site.

Open source 1

Sources

Evidence and provenance

Open MO state research →

CRG Festus Data Center Data Center Project | Festus | Compute Equity Atlas