approved
Two data center buildings of 805,000 sq ft (also stated as 800,000) plus a 40,000 sq ft administration building, roughly 1.65M sq ft total, on about 337-340 acres. MW capacity has NOT been disclosed; third-party estimates range from roughly 330 to 675 MW and servercountry.org lists a $25.5 billion figure that appears to reflect bond/equipment values rather than announced investment. Initial equipment cost reported at about $8.366 billion with roughly $8.25 billion replacement every six years. Chapter 100 documents prepared by Gilmore & Bell (Mark Grimm); Crusoe representative Conor Bates. Still requires land disturbance review and further permits. Crusoe's partners include Stargate LLC, OpenAI and Oracle, but no source confirms which customers this campus will serve. The Missouri PSC approval of Ameren's large-load rate plan was reported locally as applying to the proposed Warren County data centers.
Key data: Ameren Missouri | MISO (Ameren Missouri / AMMO)
Claim classification: Not yet assigned
Status date: 2026-09-13