under_construction
Campus planned at up to ~1.9M sq ft; power delivered by Oncor.
Key data: Oncor Electric Delivery | ERCOT
Claim classification: Not yet assigned
Status date: 2026-09-05
This record consolidates 10 research observations while retaining source distinctions, location precision and unresolved fields.
| Operator / developer | CyrusOne |
|---|---|
| Jurisdiction | Fort Worth, TX |
| Address | Asphalt Drive |
| Location precision | street address |
| Coordinates | Not published; no coordinate inferred |
| Capacity | Not established |
| Aliases | CyrusOne DFW7 · CyrusOne Fort Worth Campus · DFW7 |
| Project profile | 0 rows |
|---|---|
| Intent / permits | 0 rows |
| Civic / infrastructure | 0 rows |
Campus planned at up to ~1.9M sq ft; power delivered by Oncor.
Key data: Oncor Electric Delivery | ERCOT
Claim classification: Not yet assigned
Status date: 2026-09-05
Developer: CyrusOne | Owner: CyrusOne | County: Tarrant | Research region: Dallas-Fort Worth / North Texas
Claim classification: Not yet assigned
Status date: 2026-09-05
Key data: Utility: Oncor Electric Delivery | Grid area: ERCOT
Claim classification: Not yet assigned
Status date: 2026-09-05
Claim classification: Not yet assigned
Status date: 2026-09-05
Key data: Jurisdictions: City of Fort Worth | Tarrant County | ERCOT
Claim classification: Not yet assigned
Status date: 2026-09-05
Groundbreaking on Fort Worth campus
Claim classification: Not yet assigned
Status date: NOT_FOUND (reported at time of article)
Targeted completion of first phase
Claim classification: Not yet assigned
Status date: Q1 2026
CyrusOne broke ground on a Fort Worth campus with roughly 70 MW of initial IT load and up to 1.9M sq ft.
Key data: ~70 MW initial IT load; 1.9M sq ft
Claim classification: REPORTED_FACT · Verification: SINGLE_SOURCE · Retrieved: 2026-09-05
Filings surfaced a $200 million data center project on Asphalt Drive in Fort Worth.
Key data: $200 million
Claim classification: REPORTED_FACT · Verification: CORROBORATED · Retrieved: 2026-09-05
Power for the CyrusOne Fort Worth campus is supplied by Oncor.
Key data: Oncor Electric Delivery
Claim classification: REPORTED_FACT · Verification: SINGLE_SOURCE · Retrieved: 2026-09-05