CyrusOne Freestone County data center campus (C1 Freestone)

This record consolidates 22 research observations while retaining source distinctions, location precision and unresolved fields.

under_constructionproject status
VERIFIED_PRIMARYbest evidence tier
22linked evidence rows
Project facts

Location and operating record

Operator / developerCyrusOne; Texas Comptroller list identifies Paile, LLC as occupant/operator of the registered 'Freestone Data Center'
JurisdictionNear Fairfield, TX
AddressAdjacent to Freestone Energy Center, 1366 FM 488, Fairfield, TX 75840 (reference address for the adjacent power plant)
Location precisionparcel or bounded site
CoordinatesNot published; no coordinate inferred
Capacity760 MW
AliasesCyrusOne Freestone County data center campus (C1 Freestone) · Campus adjacent to Calpine's Freestone Energy Center, near Fairfield · Freestone Data Center · C1 Freestone, LLC Data Center · C1 Freestone 1, LLC · Reinvestment Zone Number 12
Evidence coverage

What has been researched

Project profile0 rows
Intent / permits0 rows
Civic / infrastructure2 rows
SOURCE RECORD

CyrusOne Freestone County data center campus (C1 Freestone): source record

under_construction

Rural gap find. gross_mw of 760 reflects 380 MW initial plus 380 MW phase 2 contracted with Calpine. CyrusOne is owned by KKR; Calpine is a Constellation business unit.

Key data: Calpine LLC (a Constellation business unit) providing power, grid connectivity and site infrastructure | ERCOT (North Central / East) | NOT_FOUND | NOT_FOUND

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

OWNERSHIP AND PROFILE

CyrusOne Freestone County data center campus (C1 Freestone): ownership and profile

under_construction

Developer: CyrusOne (owned by KKR) | Owner: C1 Freestone, LLC / C1 Freestone 1, LLC (CyrusOne affiliates) | Property entity: C1 Freestone 1, LLC | County: Freestone | Research region: East Texas / South Texas-RGV / Statewide Rural Gap Pass | Tenants/customers: Paile, LLC (occupant/operator on Comptroller registration) | End tenant not disclosed by CyrusOne due to confidentiality agreements

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

POWER AND GRID

CyrusOne Freestone County data center campus (C1 Freestone): power and grid

under_construction

Key data: Utility: Calpine LLC (a Constellation business unit) providing power, grid connectivity and site infrastructure | Utility region: Constellation/Calpine Freestone Energy Center | Grid area: ERCOT (North Central / East) | Gross MW: 760 | Requested load MW: 760

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

WATER AND COOLING

CyrusOne Freestone County data center campus (C1 Freestone): water and cooling

under_construction

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

PERMITS AND JURISDICTION

CyrusOne Freestone County data center campus (C1 Freestone): permits and jurisdiction

under_construction

Key data: Jurisdictions: Freestone County Commissioners Court | Texas Comptroller | ERCOT | Federal/state co-location approval obtained by Calpine (~May 2026) | Tax incentives: [object Object],[object Object] | {"agreement_name":"Reinvestment Zone Number 12 - C1 Freestone, LLC Data Center, with 10-year payment in lieu of taxes","agreement_number":"Reinvestment Zone Number 12","approval_date":"2025-12-03","estimated_value":"$850,000 per year PILOT","government_entity":"Freestone County Commissioners Court","investment_commitment":"Minimum $600 million initial property improvements","jobs_commitment":"NOT_FOUND","source_url":"https://freestonecountytimesonline.com/county-commissioners-approve-reinvestment-zone/","term":"10 years"} | {"agreement_name":"Texas Comptroller qualifying large data center registration - Freestone Data Center","agreement_number":"NOT_FOUND","approval_date":"2026-03-24 (effective date)","estimated_value":"NOT_FOUND","government_entity":"Texas Comptroller of Public Accounts","investment_commitment":"NOT_FOUND","jobs_commitment":"NOT_FOUND","source_url":"https://comptroller.texas.gov/taxes/data-centers/data-center-lists.php","term":"NOT_FOUND"}

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

CIVIC AND COMMUNITY

CyrusOne Freestone County data center campus (C1 Freestone): civic and community

under_construction

County residents raised concerns addressed at public hearings

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

under_construction

CyrusOne commitments: local career fair, Texas State Technical College MEI Data Center Pathway program, $10,000+/year scholarship

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

ENVIRONMENT AND SITE

CyrusOne Freestone County data center campus (C1 Freestone): environment and site

under_construction

Key data: Surrounding infrastructure: Calpine Freestone Energy Center: ~1 GW natural gas combined-cycle plant on ~506 acres near Fairfield

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

under_construction

Key data: Surrounding infrastructure: Existing ERCOT transmission at the power plant site

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

TIMELINE

CyrusOne Freestone County data center campus (C1 Freestone): timeline

under_construction

Freestone County Commissioners hold public hearing and unanimously approve Reinvestment Zone Number 12 for the C1 Freestone, LLC data center

Claim classification: Not yet assigned

Status date: 2025-12-03

Open source 1 →

under_construction

Constellation/Calpine and CyrusOne announce 380 MW agreement for a new data center adjacent to the Freestone Energy Center, plus an exclusive agreement for a second 380 MW phase

Claim classification: Not yet assigned

Status date: 2026-02-09

Open source 1 →

under_construction

Comptroller data center exemption effective date for Freestone Data Center (owner C1 Freestone 1, LLC; occupant Paile, LLC)

Claim classification: Not yet assigned

Status date: 2026-03-24

Open source 1 →

under_construction

Calpine secures regulatory approval to co-locate a data center at the Freestone Energy Center site

Claim classification: Not yet assigned

Status date: 2026-05

Open source 1 →

under_construction

Additional Freestone County public hearing on a proposed county reinvestment zone designation

Claim classification: Not yet assigned

Status date: 2026-06-17

Open source 1 →

under_construction

CyrusOne breaks ground on the 380 MW Freestone County campus

Claim classification: Not yet assigned

Status date: 2026-07-09

Open source 1 →

TAX INCENTIVES

CyrusOne Freestone County data center campus (C1 Freestone): tax incentives

approved

Freestone County Commissioners held a public hearing and unanimously approved Reinvestment Zone Number 12 for the C1 Freestone, LLC data center project, an affiliate of CyrusOne, covering 507 acres with a 10-year payment in lieu of taxes of $850,000 per year.

Key data: Reinvestment Zone No. 12; 507 acres; $850,000/yr PILOT for 10 years

Claim classification: official_record · Verification: primary_source · Retrieved: 2026-09-05

Status date: 2025-12-03

Limitation: The article's hearing date is printed as December 3, 2026 although it was published in December 2025; the year appears to be a typographical error.

Open source 1 →

PROJECT COST

CyrusOne Freestone County data center campus (C1 Freestone): project cost

approved

The agreement contemplates a minimum $600 million initial improvement stage, with real-property improvements potentially exceeding $2 billion and possibly double that once tenant property such as servers and chips is added.

Key data: Minimum $600M initial; >$2B potential

Claim classification: official_record · Verification: single_source · Retrieved: 2026-09-05

Status date: 2025-12-03

Limitation: CyrusOne's own page states over $500 million across phases, a lower figure.

Open source 1 →

OWNERSHIP CHAIN

CyrusOne Freestone County data center campus (C1 Freestone): ownership chain

approved

The Texas Comptroller's qualifying large data center list registers 'Freestone Data Center' effective March 24, 2026 with owner C1 Freestone 1, LLC and occupant/operator Paile, LLC.

Key data: Owner C1 Freestone 1, LLC; occupant Paile, LLC

Claim classification: official_record · Verification: primary_source · Retrieved: 2026-09-05

Status date: 2026-03-24

Limitation: Paile, LLC's ultimate parent is not disclosed in the state list.

Open source 1 →

CAPACITY GROSS POWER

CyrusOne Freestone County data center campus (C1 Freestone): capacity gross power

approved

Calpine LLC, a Constellation business unit, signed a 380 MW agreement for a new data center adjacent to the Freestone Energy Center, plus an exclusive agreement for a second 380 MW phase.

Key data: 380 MW plus 380 MW phase 2

Claim classification: official_record · Verification: primary_source · Retrieved: 2026-09-05

Status date: 2026-02-09

Limitation: Whether both phases are contracted is not fully specified.

Open source 1 →

PROJECT STATUS

CyrusOne Freestone County data center campus (C1 Freestone): project status

under_construction

CyrusOne, owned by KKR, broke ground on the Freestone County campus near Fairfield in early July 2026; Calpine had secured regulatory approval to colocate a data center at the 1 GW Freestone Energy Center site around May.

Key data: Groundbreaking early July 2026

Claim classification: reported_fact · Verification: corroborated_two_sources · Retrieved: 2026-09-05

Status date: 2026-07-09

Limitation: Exact groundbreaking date not given.

Open source 1 →

EXACT LOCATION

CyrusOne Freestone County data center campus (C1 Freestone): exact location

under_construction

CyrusOne states the facility will be near the Freestone Energy Center at 1366 FM 488, Fairfield, TX 75840; the reinvestment-zone property is described as near the Calpine power plant.

Key data: Near 1366 FM 488, Fairfield, TX 75840

Claim classification: operator_claim · Verification: corroborated_two_sources · Retrieved: 2026-09-05

Limitation: The address given is the adjacent power plant, not the data center parcel.

Open source 1 →

COMMUNITY RESPONSE

CyrusOne Freestone County data center campus (C1 Freestone): community response

under_construction

Residents raised concerns that county commissioners addressed ahead of a further reinvestment-zone public hearing scheduled for June 17, 2026.

Key data: Additional public hearing 2026-06-17

Claim classification: reported_fact · Verification: single_source · Retrieved: 2026-09-05

Status date: 2026-06-17

Limitation: Outcome of the June hearing not retrieved.

Open source 1 →

Sources

Evidence and provenance

Open TX state research →