Source-backed project record · TX

DataBank Red Oak Campus DFW9

This record consolidates 9 research observations while retaining source distinctions, location precision and unresolved fields.

under_constructionproject status
VERIFIED_PRIMARYbest evidence tier
9linked evidence rows
Project facts

Location and operating record

Operator / developerDataBank Holdings Ltd
JurisdictionRed Oak, TX
Address3080 Batchler Road
Location precisionstreet address
CoordinatesNot published; no coordinate inferred
CapacityNot established
AliasesDataBank Red Oak Campus DFW9 · DataBank Red Oak Campus · DFW9
Evidence coverage

What has been researched

Project profile0 rows
Intent / permits0 rows
Civic / infrastructure0 rows
SOURCE RECORD

DataBank Red Oak Campus DFW9: source record

under_construction

Comptroller registry lists DFW 9, 10, 11 and 12 under owner DB Data Center Red Oak LLC with Oracle America Cloud Services as occupant and DataBank Holdings Ltd as operator, effective October 1, 2025.

Key data: Oncor Electric Delivery | ERCOT

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

OWNERSHIP AND PROFILE

DataBank Red Oak Campus DFW9: ownership and profile

under_construction

Developer: DataBank | Owner: DB Data Center Red Oak LLC | Property entity: DB Data Center Red Oak LLC | County: Ellis | Research region: Dallas-Fort Worth / North Texas | Tenants/customers: Oracle America Cloud Services

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

POWER AND GRID

DataBank Red Oak Campus DFW9: power and grid

under_construction

Key data: Utility: Oncor Electric Delivery | Grid area: ERCOT | Substations: 400 MW Oncor substation serving Phase 1

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

WATER AND COOLING

DataBank Red Oak Campus DFW9: water and cooling

under_construction

Key data: Cooling: supports rear-door heat exchangers and water-to-chip liquid cooling

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

PERMITS AND JURISDICTION

DataBank Red Oak Campus DFW9: permits and jurisdiction

under_construction

Key data: Jurisdictions: City of Red Oak | Ellis County | ERCOT | Tax incentives: [object Object] | {"agreement_name":"Ellis County tax abatement agreement","agreement_number":"NOT_FOUND","approval_date":"NOT_FOUND","estimated_value":"NOT_FOUND","government_entity":"Ellis County","investment_commitment":"NOT_FOUND","jobs_commitment":"NOT_FOUND","source_url":"https://www.midlothianmirror.com/court-approves-data-center-abatement/","term":"7 years"}

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

ENVIRONMENT AND SITE

DataBank Red Oak Campus DFW9: environment and site

under_construction

Campus marketed as 100% renewable-powered

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

TIMELINE

DataBank Red Oak Campus DFW9: timeline

under_construction

Campus announced

Claim classification: Not yet assigned

Status date: 2024-09-10

Open source 1 →

under_construction

Ellis County Commissioners Court approves abatement to Databank Datacenters, LLC

Claim classification: Not yet assigned

Open source 1 →

under_construction

DFW9 ready for service target

Claim classification: Not yet assigned

Status date: Q2 2026

Open source 1 →

Sources

Evidence and provenance

Open TX state research →

DataBank Red Oak Campus DFW9 Data Center Project | Red Oak | Compute Equity Atlas