Element Critical Houston One

This record consolidates 17 research observations while retaining source distinctions, location precision and unresolved fields.

operationalproject status
CORROBORATEDbest evidence tier
17linked evidence rows
Project facts

Location and operating record

Operator / developerElement Critical
JurisdictionKaty, TX
Address22000 Franz Road
Location precisionstreet address
CoordinatesNot published; no coordinate inferred
Capacity32 MW
AliasesElement Critical Houston One · Houston One · Skybox Houston One · Houston One HPC data center
Evidence coverage

What has been researched

Project profile0 rows
Intent / permits0 rows
Civic / infrastructure0 rows
SOURCE RECORD

Element Critical Houston One: source record

operational

Sources conflict on site acreage (10 acres in the Element Critical facility PDF vs 20 acres on Baxtel) and on capacity (26MW vs 32MW post-expansion). LEED Gold certified, Tier III concurrently maintainable.

Key data: CenterPoint Energy; renewable PPA with NextEra Energy (wind) for Texas data centers | ERCOT | NOT_FOUND

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

LOCATION AND PROJECT EVIDENCE

Element Critical Houston One: location and project evidence

Source update

Element Critical describes Houston Two as an expansion under construction at the same 22000 Franz Road campus as Houston One. The expansion is linked to this existing campus location without changing Houston One’s operating status or treating planned expansion power as current load.

Claim classification: PRIMARY_SOURCE_OBSERVATION · Verification: FIELD_SCOPED_SOURCE_REVIEW · Retrieved: 2026-10-01

Status date: 2026-10-01

Limitation: Power capacity and other measurements are not inferred from site identity or construction forecasts.

Open source 1 →

OWNERSHIP AND PROFILE

Element Critical Houston One: ownership and profile

operational

Developer: Skybox Datacenters (original developer) | Owner: Element Critical | County: Harris | Research region: Houston / Gulf Coast | Tenants/customers: Fugro (2,350 sq ft remote operations center)

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

POWER AND GRID

Element Critical Houston One: power and grid

operational

Key data: Utility: CenterPoint Energy; renewable PPA with NextEra Energy (wind) for Texas data centers | Utility region: ERCOT Houston (Coast) load zone | Grid area: ERCOT | Gross MW: 32 | IT load MW: 26

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

WATER AND COOLING

Element Critical Houston One: water and cooling

operational

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

PERMITS AND JURISDICTION

Element Critical Houston One: permits and jurisdiction

operational

Key data: Jurisdictions: Harris County | City of Katy / Houston ETJ

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

TIMELINE

Element Critical Houston One: timeline

operational

Element Critical acquires Houston One from Skybox Datacenters

Claim classification: Not yet assigned

Status date: 2021-03-16

Open source 1 →

operational

Element Critical completes expansion adding two data halls / 20,000 sq ft, bringing capacity to 32MW

Claim classification: Not yet assigned

Status date: 2022-05-12

Open source 1 →

operational

Fugro leases 2,350 sq ft for a remote operations center

Claim classification: Not yet assigned

Status date: 2024-10-23

Open source 1 →

operational

Element Critical breaks ground on further 10MW expansion (new 20,000 sq ft data hall); 4.5MW live target

Claim classification: Not yet assigned

Status date: 2025-11-19

Open source 1 →

OWNERSHIP CHAIN

Element Critical Houston One: ownership chain

operational

Element Critical announced on March 16, 2021 the acquisition of Skybox Datacenters' Houston One high-performance computing facility at 22000 Franz Road, Katy.

Key data: Acquired from Skybox Datacenters 2021-03-16

Claim classification: OFFICIAL_RECORD · Verification: PRIMARY_SOURCE · Retrieved: 2026-09-05

Status date: 2021-03-16

Open source 1 →

CAPACITY GROSS POWER

Element Critical Houston One: capacity gross power

operational

Element Critical completed an expansion adding two data halls and 20,000 sq ft of colocation space, bringing the facility to 32MW.

Key data: 32MW after 2022 expansion; +20,000 sq ft

Claim classification: REPORTED_FACT · Verification: CORROBORATED · Retrieved: 2026-09-05

Status date: 2022-05-12

Limitation: CONFLICT: other sources describe the facility at 26MW / 118,250 sq ft; the 32MW figure post-dates the 2022 expansion.

Open source 1 →

POWER SUPPLIER

Element Critical Houston One: power supplier

operational

Element Critical signed a power purchase agreement with NextEra Energy to supply its Texas data centers with wind-generated renewable energy.

Key data: NextEra Energy wind PPA

Claim classification: REPORTED_FACT · Verification: SINGLE_SOURCE · Retrieved: 2026-09-05

Status date: 2022-05-12

Open source 1 →

BUILDING SQFT

Element Critical Houston One: building sqft

operational

An Element Critical facility datasheet records Houston One (22000 Franz Road, Katy 77449) as a Tier III concurrently maintainable, LEED Gold certified building of 118,248 sq ft on 10 acres.

Key data: 118,248 sq ft on 10 acres; Tier III; LEED Gold

Claim classification: COMPANY_CLAIM · Verification: CONFLICTING · Retrieved: 2026-09-05

Status date: 2026-09-05

Limitation: CONFLICT: Baxtel lists a 20-acre lot for the same site.

Open source 1 →

PROJECT TIMELINE

Element Critical Houston One: project timeline

under_construction

Element Critical broke ground in November 2025 on a further 10MW expansion, adding a new 20,000 sq ft data hall with 4.5MW targeted live in Q4 2026.

Key data: +10MW expansion; 4.5MW live Q4 2026

Claim classification: REPORTED_FACT · Verification: SINGLE_SOURCE · Retrieved: 2026-09-05

Status date: 2025-11-19

Open source 1 →

TENANT CUSTOMER

Element Critical Houston One: tenant customer

operational

Fugro leased 2,350 sq ft at the facility for a remote operations center supporting onshore growth in Houston.

Key data: Fugro, 2,350 sq ft remote operations center

Claim classification: REPORTED_FACT · Verification: SINGLE_SOURCE · Retrieved: 2026-09-05

Status date: 2024-10-23

Open source 1 →

SURROUNDING INFRASTRUCTURE

Element Critical Houston One: surrounding infrastructure

operational

The Franz Road facility is built around 10,000 sq ft private data halls, each with its own dedicated back-end infrastructure.

Key data: 10,000 sq ft private data halls with dedicated infrastructure

Claim classification: AGGREGATOR_LISTING · Verification: SINGLE_SOURCE · Retrieved: 2026-09-05

Status date: 2026-09-05

Open source 1 →