under_construction
County conflict: isadatacentercoming.com lists Potter County; TCEQ permit documents list Carson County - TCEQ (Tier-1) is authoritative. Directory listings enumerate buildings Project Matador D1 through D7. Grid area is SPP (SPS/Xcel), not ERCOT.
Key data: Southwestern Public Service Company (SPS), an Xcel Energy company | SPP (Southwest Power Pool) via SPS 115 kV network - NOT ERCOT; plus planned private behind-the-meter generation | City of Amarillo | NOT_FOUND
Claim classification: Not yet assigned
Status date: 2026-09-05