planned
Three buildings planned; described as Flexential's fourth and largest DFW facility. The site was released from Talty's ETJ, placing it under county jurisdiction.
Key data: ERCOT
Claim classification: Not yet assigned
Status date: 2026-09-05
This record consolidates 10 research observations while retaining source distinctions, location precision and unresolved fields.
| Operator / developer | Flexential |
|---|---|
| Jurisdiction | Talty (outside city jurisdiction after ETJ release), TX |
| Address | Not published |
| Location precision | locality centroid |
| Coordinates | 32.694439, -96.400763 |
| Capacity | Not established |
| Aliases | Flexential Talty Campus · Talty Campus |
| Project profile | 0 rows |
|---|---|
| Intent / permits | 0 rows |
| Civic / infrastructure | 0 rows |
Three buildings planned; described as Flexential's fourth and largest DFW facility. The site was released from Talty's ETJ, placing it under county jurisdiction.
Key data: ERCOT
Claim classification: Not yet assigned
Status date: 2026-09-05
Developer: Flexential | Owner: Flexential | County: Kaufman | Research region: Dallas-Fort Worth / North Texas
Claim classification: Not yet assigned
Status date: 2026-09-05
Key data: Grid area: ERCOT
Claim classification: Not yet assigned
Status date: 2026-09-05
Claim classification: Not yet assigned
Status date: 2026-09-05
Key data: Jurisdictions: Kaufman County (site released from Talty ETJ) | ERCOT
Claim classification: Not yet assigned
Status date: 2026-09-05
Construction targeted to begin
Claim classification: Not yet assigned
Status date: early 2027
Customers targeted to come online
Claim classification: Not yet assigned
Status date: late 2028
Flexential plans a 110-acre, three-building campus in Talty totaling 108 MW, with a 36 MW first phase of 375,000 sq ft.
Key data: 108 MW total; 36 MW / 375,000 sq ft first phase; 110 acres
Claim classification: REPORTED_FACT · Verification: SINGLE_SOURCE · Retrieved: 2026-09-05
Status date: 2026
Construction is targeted for early 2027 with customers online in late 2028.
Key data: construction early 2027; customers late 2028
Claim classification: REPORTED_FACT · Verification: SINGLE_SOURCE · Retrieved: 2026-09-05
Status date: 2026
The site sits outside city jurisdiction after being released from Talty's extraterritorial jurisdiction.
Key data: released from Talty ETJ; county jurisdiction
Claim classification: REPORTED_FACT · Verification: SINGLE_SOURCE · Retrieved: 2026-09-05
Status date: 2026