Forney Compute Facility

This record consolidates 15 research observations while retaining source distinctions, location precision and unresolved fields.

proposed_or_reviewproject status
SOURCE_BACKEDbest evidence tier
15linked evidence rows
Project facts

Location and operating record

Operator / developerNOT_FOUND
JurisdictionForney, TX
AddressEast of FM 1641, approximately 1,100 ft from the Fox Hollow neighborhood
Location precisionparcel or bounded site
CoordinatesNot published; no coordinate inferred
CapacityNot established
AliasesForney Compute Facility
Evidence coverage

What has been researched

Project profile0 rows
Intent / permits0 rows
Civic / infrastructure3 rows
SOURCE RECORD

Forney Compute Facility: source record

planned

Small ~20 MW compute facility that became a flashpoint in Forney's data center politics.

Key data: Oncor Electric Delivery | ERCOT

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

OWNERSHIP AND PROFILE

Forney Compute Facility: ownership and profile

planned

Developer: Basic Developers, LLC | Permit applicant: Basic Developers, LLC (agent Daniel Stewart) | County: Kaufman | Research region: Dallas-Fort Worth / North Texas

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

POWER AND GRID

Forney Compute Facility: power and grid

planned

Key data: Utility: Oncor Electric Delivery | Grid area: ERCOT | Transmission: Oncor overhead lines using capacity freed by the Smurfit Kappa facility

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

WATER AND COOLING

Forney Compute Facility: water and cooling

planned

Key data: Cooling: closed-loop cooling | Wastewater: on-site septic system

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

PERMITS AND JURISDICTION

Forney Compute Facility: permits and jurisdiction

planned

Key data: Jurisdictions: City of Forney | Kaufman County | ERCOT

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

CIVIC AND COMMUNITY

Forney Compute Facility: civic and community

planned

Sited roughly 1,100 ft from the Fox Hollow neighborhood

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

planned

P&Z deadlock effectively denied the application

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

planned

Forney moving toward a citywide data center prohibition via zoning text amendment

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

TIMELINE

Forney Compute Facility: timeline

planned

Forney Ordinance 26-12 adopted requiring a 5,000-ft residential setback

Claim classification: Not yet assigned

Status date: 2026-04

Open source 1 →

planned

Planning & Zoning Commission deadlocks 3-3, constituting denial

Claim classification: Not yet assigned

Status date: 2026-06-04

Open source 1 →

planned

Appeal heard by City Council requiring a three-fourths supermajority

Claim classification: Not yet assigned

Status date: 2026-07-21

Open source 1 →

PROJECT STATUS

Forney Compute Facility: project status

planned

Forney's Planning & Zoning Commission deadlocked 3-3 on June 4, 2026, which constituted a denial, and the appeal went to City Council on July 21, 2026 requiring a three-fourths supermajority.

Key data: P&Z 3-3 deadlock = denial; council appeal 2026-07-21

Claim classification: REPORTED_FACT · Verification: SINGLE_SOURCE · Retrieved: 2026-09-05

Status date: 2026-07-21

Limitation: Local blog-style coverage; not confirmed against official Forney meeting minutes.

Open source 1 →

CAPACITY GROSS POWER

Forney Compute Facility: capacity gross power

planned

The 5.4-acre, roughly 60,000 sq ft facility would draw about 20 MW, which the city compared to 16,000-20,000 homes.

Key data: ~20 MW; 5.4 acres; ~60,000 sq ft

Claim classification: REPORTED_FACT · Verification: SINGLE_SOURCE · Retrieved: 2026-09-05

Status date: 2026

Open source 1 →

INTERCONNECTION

Forney Compute Facility: interconnection

planned

Power would come via Oncor overhead lines using capacity freed by the Smurfit Kappa facility.

Key data: Oncor lines; capacity freed by Smurfit Kappa

Claim classification: REPORTED_FACT · Verification: SINGLE_SOURCE · Retrieved: 2026-09-05

Status date: 2026

Open source 1 →

ZONING LAND USE

Forney Compute Facility: zoning land use

planned

Forney Ordinance 26-12, adopted in April 2026, requires a 5,000-foot setback from residences; the proposed site is about 1,100 feet from the Fox Hollow neighborhood.

Key data: Ordinance 26-12; 5,000-ft setback; site ~1,100 ft from homes

Claim classification: REPORTED_FACT · Verification: SINGLE_SOURCE · Retrieved: 2026-09-05

Status date: 2026-04

Open source 1 →