Galaxy McGregor AI Data Center Campus

This record consolidates 13 research observations while retaining source distinctions, location precision and unresolved fields.

approved_or_permittedproject status
VERIFIED_PRIMARYbest evidence tier
13linked evidence rows
Project facts

Location and operating record

Operator / developerGalaxy Digital Inc.
JurisdictionMcGregor, TX
AddressMcGregor Industrial Park
Location precisionparcel or bounded site
CoordinatesNot published; no coordinate inferred
CapacityNot established
AliasesGalaxy McGregor AI Data Center Campus · McGregor Industrial Park campus (Project Merlin) · Project Merlin · Galaxy Digital McGregor campus
Evidence coverage

What has been researched

Project profile0 rows
Intent / permits0 rows
Civic / infrastructure2 rows
SOURCE RECORD

Galaxy McGregor AI Data Center Campus: source record

approved

Structured as a 'new grid model' deal: cooperative-served load with a developer-funded private substation and no tax abatement.

Key data: Heart of Texas Electric Cooperative (HOTEC) | ERCOT | NOT_FOUND | NOT_FOUND

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

OWNERSHIP AND PROFILE

Galaxy McGregor AI Data Center Campus: ownership and profile

approved

Developer: Galaxy Digital Inc. | Owner: Galaxy Digital Inc. (acquired the campus 2026-07-28) | Permit applicant: Galaxy Digital (development agreement with the City of McGregor) | County: McLennan | Research region: Temple-Killeen-Waco / Bryan-College Station / Texoma

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

POWER AND GRID

Galaxy McGregor AI Data Center Campus: power and grid

approved

Key data: Utility: Heart of Texas Electric Cooperative (HOTEC) | Utility region: ERCOT | Grid area: ERCOT | Substations: Galaxy funds and builds its own private on-site substation | Grid/market records: Coordination required above the 75 MW ERCOT large-load threshold

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

WATER AND COOLING

Galaxy McGregor AI Data Center Campus: water and cooling

approved

Key data: Water demand: ~3,000 gallons per day per powered shell (closed-loop) | Cooling: Closed-loop cooling

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

PERMITS AND JURISDICTION

Galaxy McGregor AI Data Center Campus: permits and jurisdiction

approved

Key data: Jurisdictions: State of Texas | McLennan County | City of McGregor | McGregor EDC | HOTEC service territory | ERCOT | Tax incentives: [object Object] | {"agreement_name":"City of McGregor development agreement (no property tax abatement)","agreement_number":"NOT_FOUND","approval_date":"2026-07-28","estimated_value":"No property tax abatement; at least $130M added to the tax base","government_entity":"City of McGregor; McGregor Economic Development Corporation","investment_commitment":"More than $400 million","jobs_commitment":"At least 30 full-time jobs at >$60,000 average pay","source_url":"https://www.galaxy.com/newsroom/galaxy-expands-data-center-footprint-with-acquisition-of-500-acre-campus-in-mcgregor-texas","term":"NOT_FOUND"}

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

CIVIC AND COMMUNITY

Galaxy McGregor AI Data Center Campus: civic and community

approved

Noise limited to 65 dBA using 11-inch precast walls

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

approved

No property tax abatement sought

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

ENVIRONMENT AND SITE

Galaxy McGregor AI Data Center Campus: environment and site

approved

Closed-loop cooling with roughly 3,000 gallons/day per powered shell

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

approved

Key data: Surrounding infrastructure: McGregor Industrial Park

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

approved

Key data: Surrounding infrastructure: Heart of Texas Electric Cooperative distribution and a new private substation

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

TIMELINE

Galaxy McGregor AI Data Center Campus: timeline

approved

Galaxy acquires the ~500-acre McGregor campus for ~$7.5M in land-sale revenue to the city

Claim classification: Not yet assigned

Status date: 2026-07-28

Open source 1 →

approved

First power targeted

Claim classification: Not yet assigned

Status date: 2028

Open source 1 →

approved

Growth to multi-hundred MW through 2030

Claim classification: Not yet assigned

Status date: 2030

Open source 1 →