An intervenor letter to the commission identifies the docket, the specific filing and the terms at issue in the OpenAI large-load contract
Key data: Georgia PSC Docket No. 44280 (Georgia Power 2022 Rate Case); Document Filing #227259, "Large Load Contract Filing - 7.15.26"; 3.2 gigawatt projected OpenAI load requiring roughly 3,000 MW of generation; intervenors urged a 500 MW / $1 billion approval threshold, minimum billing demand of at least 80 percent (90 percent under consideration) and contract terms of at least twenty years; objection deadline August 14, 2026
Limitation: This is an intervenor filing, not a commission order; the recommended terms are advocacy positions, not approved conditions