operational
First building constructed at the Midlothian campus
Claim classification: Not yet assigned
Status date: 2019
Open source 1 →
operational
Building 4 constructed, 170,600 sq ft, $100 million
Claim classification: Not yet assigned
Status date: 2024
Open source 1 →
operational
Building 5 TDLR project registered
Claim classification: Not yet assigned
Status date: 2025-12-08
Open source 1 →
operational
Building 5 construction start (TDLR)
Claim classification: Not yet assigned
Status date: 2026-01-28
Open source 1 →
operational
Building 5 estimated completion (TDLR)
Claim classification: Not yet assigned
Status date: 2027-02-24
Open source 1 →