approved
Five buildings in two phases. Acreage conflicts between trade press (107 ac) and TDLR filing (77 ac).
Key data: Oncor Electric Delivery (private substation planned) | ERCOT
Claim classification: Not yet assigned
Status date: 2026-09-05
This record consolidates 10 research observations while retaining source distinctions, location precision and unresolved fields.
| Operator / developer | NOT_FOUND |
|---|---|
| Jurisdiction | Fort Worth, TX |
| Address | Hicks Field Road |
| Location precision | street address |
| Coordinates | Not published; no coordinate inferred |
| Capacity | Not established |
| Aliases | Grupo ACS Fort Worth Data Center Campus · Hicks Field Road Campus |
| Project profile | 0 rows |
|---|---|
| Intent / permits | 0 rows |
| Civic / infrastructure | 0 rows |
Five buildings in two phases. Acreage conflicts between trade press (107 ac) and TDLR filing (77 ac).
Key data: Oncor Electric Delivery (private substation planned) | ERCOT
Claim classification: Not yet assigned
Status date: 2026-09-05
Developer: Grupo ACS (Spanish infrastructure group) | Owner: Grupo ACS affiliate | Permit applicant: Grupo ACS affiliate (TDLR filing) | County: Tarrant | Research region: Dallas-Fort Worth / North Texas
Claim classification: Not yet assigned
Status date: 2026-09-05
Key data: Utility: Oncor Electric Delivery (private substation planned) | Grid area: ERCOT | Substations: Private on-site substation planned
Claim classification: Not yet assigned
Status date: 2026-09-05
Claim classification: Not yet assigned
Status date: 2026-09-05
Key data: Permit IDs: TDLR filing valued at $100M for construction Aug 6 2026 - May 17 2028 | Jurisdictions: City of Fort Worth | Tarrant County | ERCOT | Tax incentives: [object Object] | {"agreement_name":"Economic Development Program (EDP) agreement, City of Fort Worth","agreement_number":"NOT_FOUND","approval_date":"NOT_FOUND","estimated_value":"35% to 70% rebate of business personal property taxes","government_entity":"City of Fort Worth","investment_commitment":"at least $2 billion","jobs_commitment":"37 jobs at >$150k average salary","source_url":"https://www.commercialsearch.com/news/2b-data-center-project-moves-forward-in-fort-worth/","term":"10 years"}
Claim classification: Not yet assigned
Status date: 2026-09-05
Fort Worth advances incentive agreement for $2B campus
Claim classification: Not yet assigned
Status date: 2026
TDLR construction filing (start)
Claim classification: Not yet assigned
Status date: 2026-08-06
TDLR construction filing (completion)
Claim classification: Not yet assigned
Status date: 2028-05-17
Phase 1 targeted completion
Claim classification: Not yet assigned
Status date: end of 2031
Phase 2 targeted completion
Claim classification: Not yet assigned
Status date: end of 2034