Approved over opposition
Contested approval: the Planning Commission **denied** the deferred plan at its Nov 5, 2025 meeting (after Sept 24 and Oct 29 deferrals with the hearing closed), and the Board of County Supervisors later approved the rezoning and SUP **4–3** (nays: Stewart, Vega, Chair Jefferson) after dozens of speakers and more than an hour of debate. Opponents (neighbors, environmental advocates, local retailers) cited diesel generators, air, noise, electricity demand, and loss of mixed-use frontage; Elena Schlossberg told the board "Vote no on Hornbaker. Enough is enough."
Key data: Planning Commission denial 2025-11-05; BOCS approval 4–3; ±40.02 acres from A-1/PBD to M-2
Status date: 2026 (BOCS vote)
Limitation: County agenda (primary) confirms case number and acreage/zoning change; the vote tally comes from meeting coverage.