planned
Capacity conflicts: Entergy and Hut 8 state 330 MW utility capacity / 245 MW critical IT with up to 1,000 MW potential; Data Center Map lists 300 MW utility / 200 MW IT and 592 acres. Acreage conflicts: 592 acres secured (Hut 8, Mar 2025) vs 627 acres and 2,361 acres under option (Hut 8 site page). Status left 'planned': parish approval, leases and financing are documented, and site/water work is reported, but no fetched source confirms a construction start date; Entergy states operations are expected in Q2 2027.
Key data: Entergy Louisiana, LLC | Local water system; $16M in water infrastructure (new well and ~8 miles of water main) announced May 2026
Claim classification: Not yet assigned
Status date: 2026-09