Committed
Hut 8 committed approximately $16 million on May 19, 2026 to build a new well and about eight miles of water main, to be transferred to West Feliciana Parish at no cost to taxpayers, potentially serving more than 4,000 households and 200 businesses. The facility uses closed-loop recirculating cooling requiring an initial charge equivalent to three to four Olympic pools — reported as approximately 2.3 million gallons. Hut 8's own release does not state a gallons-per-day capacity.
Key data: $16M water infrastructure commitment; ~8 miles of main; initial closed-loop fill ≈2.3 million gallons
Status date: 2026-05-19
Limitation: Ongoing operational water volume and added gpd capacity are not disclosed in any fetched source; an independent estimate suggests 951,000–3.4 MGD *if* evaporative cooling were used, which contradicts the stated closed-loop design