under_construction
COUNTY CONFLICT: IREN brands the campus 'Sweetwater' (Sweetwater city is in Nolan County) while DatacenterDynamics reports the sites are in Fisher County outside Sweetwater. Sweetwater 1 = 1,400 MW on 1,700 acres, substation energization 2026; Sweetwater 2 = 600 MW on 500 acres, IREN targets 2027 energization while DCD reports 2028. Microsoft is a major IREN customer but was not confirmed as a Sweetwater tenant in any source fetched.
Key data: Direct ERCOT connection | ERCOT
Claim classification: Not yet assigned
Status date: 2026-09-05