Iron Mountain Hutto data center campus

This record consolidates 8 research observations while retaining source distinctions, location precision and unresolved fields.

proposed_or_reviewproject status
SOURCE_BACKEDbest evidence tier
8linked evidence rows
Project facts

Location and operating record

Operator / developerIron Mountain Data Centers
JurisdictionHutto, TX
AddressFM 3349 (County Road 404), south of the Samsung Taylor fab
Location precisionparcel or bounded site
CoordinatesNot published; no coordinate inferred
CapacityNot established
AliasesIron Mountain Hutto data center campus · FM 3349 / County Road 404 campus, Hutto · Iron Mountain Austin campus · Iron Mountain Hutto
Evidence coverage

What has been researched

Project profile0 rows
Intent / permits0 rows
Civic / infrastructure0 rows
SOURCE RECORD

Iron Mountain Hutto data center campus: source record

planned

Seven buildings on roughly 500 acres. The low sanitary-sewer request (30,200 gal/day) is consistent with a largely closed-loop or air-cooled design, but no cooling technology has been formally filed.

Key data: NOT_FOUND | ERCOT South Central / Austin-Central Texas load zone | NOT_FOUND | NOT_FOUND

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

OWNERSHIP AND PROFILE

Iron Mountain Hutto data center campus: ownership and profile

planned

Developer: Iron Mountain Incorporated | County: Williamson | Research region: Austin / Central Texas | Tenants/customers: Not disclosed

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

POWER AND GRID

Iron Mountain Hutto data center campus: power and grid

planned

Key data: Utility region: ERCOT | Grid area: ERCOT South Central / Austin-Central Texas load zone | Substations: On-site substation proposed as part of the campus

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

WATER AND COOLING

Iron Mountain Hutto data center campus: water and cooling

planned

Key data: Wastewater: Sanitary sewer application for approximately 30,200 gallons/day filed with the City of Hutto in March 2026

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

PERMITS AND JURISDICTION

Iron Mountain Hutto data center campus: permits and jurisdiction

planned

Key data: Jurisdictions: City of Hutto | Williamson County | ERCOT

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

TIMELINE

Iron Mountain Hutto data center campus: timeline

planned

Sanitary sewer service application (~30,200 gal/day) filed with the City of Hutto

Claim classification: Not yet assigned

Status date: 2026-03-01

Open source 1 →

planned

Data Center Dynamics reports Iron Mountain eyeing a seven-building campus outside Austin

Claim classification: Not yet assigned

Status date: 2026-01-01

Open source 1 →

planned

First grid-connected buildings targeted around 2030

Claim classification: Not yet assigned

Status date: 2030-01-01

Open source 1 →