announced
Geronimo Power's own project page states the data center would use approximately 400 MW of electricity, recorded here as requested_load_mw; a third-party tracker (cleanview.co) lists 450 MW - conflict preserved. Acreage and building size are undetermined. Jasper County has no zoning, so no rezoning approval is required; the county commission's role is limited to road and decommissioning agreements (Commissioner Jimmy Morris). Geronimo cites Missouri Senate Bill 4 for the proposition that local electric rates cannot be increased because of a large-load customer. The associated solar farm has been reported at roughly 2,000 acres with 640 acres leased in Lawrence County. Utility territory (Liberty Utilities / Empire District) is per missouridatacenters.org, not a utility filing.
Key data: Liberty Utilities (Empire District) | Not verified in fetched sources
Claim classification: Not yet assigned
Status date: 2026-09-13