Source-backed project record · MO

Jasper County Powered Data Park

This record consolidates 17 research observations while retaining source distinctions, location precision and unresolved fields.

proposed_or_reviewproject status
CORROBORATEDbest evidence tier
17linked evidence rows
Project facts

Location and operating record

Operator / developerGeronimo Power (Bloomington, Minnesota)
JurisdictionLa Russell (unincorporated eastern Jasper County, near Sarcoxie), MO
AddressLand west of Missouri Highway 96, south of the La Russell Energy Center, near Fir Road
Location precisionparcel or bounded site
CoordinatesNot published; no coordinate inferred
CapacityNot established
AliasesJasper County Powered Data Park · Geronimo Jasper County data center · Sarcoxie / La Russell data center
Evidence coverage

What has been researched

Project profile0 rows
Intent / permits0 rows
Civic / infrastructure5 rows
SOURCE RECORD

Jasper County Powered Data Park: source record

announced

Geronimo Power's own project page states the data center would use approximately 400 MW of electricity, recorded here as requested_load_mw; a third-party tracker (cleanview.co) lists 450 MW - conflict preserved. Acreage and building size are undetermined. Jasper County has no zoning, so no rezoning approval is required; the county commission's role is limited to road and decommissioning agreements (Commissioner Jimmy Morris). Geronimo cites Missouri Senate Bill 4 for the proposition that local electric rates cannot be increased because of a large-load customer. The associated solar farm has been reported at roughly 2,000 acres with 640 acres leased in Lawrence County. Utility territory (Liberty Utilities / Empire District) is per missouridatacenters.org, not a utility filing.

Key data: Liberty Utilities (Empire District) | Not verified in fetched sources

Claim classification: Not yet assigned

Status date: 2026-09-13

Open source 1

OWNERSHIP AND PROFILE

Jasper County Powered Data Park: ownership and profile

announced

Developer: Geronimo Power (Bloomington, Minnesota) | County: Jasper | Research region: Southwest Missouri

Claim classification: Not yet assigned

Status date: 2026-09-13

Open source 1

POWER AND GRID

Jasper County Powered Data Park: power and grid

announced

Key data: Utility: Liberty Utilities (Empire District) | Grid area: Not verified in fetched sources | Requested load MW: 400

Claim classification: Not yet assigned

Status date: 2026-09-13

Open source 1

announced

Geronimo Power's project page states the Jasper County Powered Data Park would use approximately 400 MW of electricity, sited west of Missouri Highway 96 south of the La Russell Energy Center, with closed-loop cooling that may be air-based or water-based and backup generators used only for emergencies and testing.

Key data: ~400 MW electricity use

Claim classification: proposal_or_announced_commitment · Verification: verified_by_primary_source · Retrieved: 2026-09-13

Status date: 2026-03

Limitation: Developer self-report at an early stage; cooling method, building count and end user are undetermined.

Open source 1

WATER AND COOLING

Jasper County Powered Data Park: water and cooling

announced

Key data: Water demand: Not yet determined; minimal water use stated as a core design principle | Cooling: Closed-loop cooling, either air-based or water-based; recirculating sealed cycle

Claim classification: Not yet assigned

Status date: 2026-09-13

Open source 1

PERMITS AND JURISDICTION

Jasper County Powered Data Park: permits and jurisdiction

announced

Key data: Jurisdictions: Jasper County (no county zoning) | Missouri

Claim classification: Not yet assigned

Status date: 2026-09-13

Open source 1

CIVIC AND COMMUNITY

Jasper County Powered Data Park: civic and community

announced

Opposition group Southwest Missouri Citizens Against Data Centers formed

Claim classification: Not yet assigned

Status date: 2026-09-13

Open source 1

announced

A Sarcoxie community meeting drew 175-200 people

Claim classification: Not yet assigned

Status date: 2026-09-13

Open source 1

announced

Dedicated local charitable fund of millions of dollars over the first 20 years; $750,000 over 20 years attached to the solar project

Claim classification: Not yet assigned

Status date: 2026-09-13

Open source 1

CORROBORATED

The Joplin Globe reported that Minnesota-based Geronimo Power planned a data center park in eastern Jasper County, meeting the Sarcoxie City Council on 2026-03-03 and Jasper County commissioners in March 2026; Jasper County has no zoning, so the commission's role is limited to road and decommissioning agreements.

Key data: Jasper County has no zoning authority over the site

Claim classification: documented_fact · Verification: source_backed_unverified · Retrieved: 2026-09-13

Limitation: No formal application exists to review; details may change.

Open source 1

CORROBORATED

Southwest Missouri Citizens Against Data Centers announced opposition to the large-scale AI data center and solar park projects; Sarcoxie community meetings drew 175 to 200 people.

Key data: Opposition group formed; meetings of 175-200 people

Claim classification: reported_perception · Verification: source_backed_unverified · Retrieved: 2026-09-13

Limitation: Attendance figures are reported estimates.

Open source 1

ENVIRONMENT AND SITE

Jasper County Powered Data Park: environment and site

announced

Key data: Surrounding infrastructure: La Russell Energy Center provides transmission infrastructure

Claim classification: Not yet assigned

Status date: 2026-09-13

Open source 1

announced

Key data: Surrounding infrastructure: Companion Spring River Solar & Storage project of 150 MW sited just north of the La Russell Energy Center, spanning Jasper and Lawrence counties

Claim classification: Not yet assigned

Status date: 2026-09-13

Open source 1

TIMELINE

Jasper County Powered Data Park: timeline

announced

Geronimo representatives met with the Sarcoxie City Council

Claim classification: Not yet assigned

Status date: 2026-03-03

Open source 1

announced

Geronimo met Jasper County commissioners to discuss a data center south of the La Russell Energy Center

Claim classification: Not yet assigned

Status date: 2026-03

Open source 1

announced

Geronimo presented the companion solar farm plan to Lawrence County commissioners

Claim classification: Not yet assigned

Status date: 2026-03-31

Open source 1

announced

Southwest Missouri Citizens Against Data Centers announced opposition

Claim classification: Not yet assigned

Status date: 2026-05-29

Open source 1

Sources

Evidence and provenance

Open MO state research →

Jasper County Powered Data Park Data Center Project | La Russell (unincorporated eastern Jasper County, near Sarcoxie) | Compute Equity Atlas