Source-backed project record · TX

Lacy Lakeview Data District (L2D2)

This record consolidates 25 research observations while retaining source distinctions, location precision and unresolved fields.

proposed_or_reviewproject status
CORROBORATEDbest evidence tier
25linked evidence rows
Project facts

Location and operating record

Operator / developerInfrakey DC Parks LLC
JurisdictionLacy Lakeview / Elm Mott (unincorporated site in Waco's ETJ), TX
AddressNOT_FOUND
Location precisionparcel or bounded site
CoordinatesNot published; no coordinate inferred
CapacityNot established
AliasesLacy Lakeview Data District (L2D2) · L2D2 - 520-acre district west of Elm Mott · L2D2 · Infrakey DC Parks data center district · Lacy Lakeview data center district
Evidence coverage

What has been researched

Project profile0 rows
Intent / permits0 rows
Civic / infrastructure2 rows
SOURCE RECORD

Lacy Lakeview Data District (L2D2): source record

announced

Leadership named in reporting: chair Bill Barney, CEO Braham Singh, and Sujeeth Draksharam. Developer-published milestones are self-reported and were not confirmed against ERCOT or Brazos Electric records.

Key data: Direct ERCOT interconnection per developer; 'Construction Permission from Brazos' milestone references Brazos Electric | ERCOT | NOT_FOUND | NOT_FOUND

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

OWNERSHIP AND PROFILE

Lacy Lakeview Data District (L2D2): ownership and profile

announced

Developer: Infrakey DC Parks LLC (Infrakey Global) | Property entity: Infrakey DC Parks LLC | Permit applicant: Infrakey DC Parks LLC (public-private partnership counterparty with the City of Lacy Lakeview) | County: McLennan | Research region: Temple-Killeen-Waco / Bryan-College Station / Texoma

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

POWER AND GRID

Lacy Lakeview Data District (L2D2): power and grid

announced

Key data: Utility: Direct ERCOT interconnection per developer; 'Construction Permission from Brazos' milestone references Brazos Electric | Utility region: ERCOT | Grid area: ERCOT | Substations: On-site substation planned | Transmission: 19-20 mile natural gas pipeline needed from the Hillsboro area to serve the on-site plant | Grid/market records: Interconnection request dated 2024-10-01 per developer milestone list | PCPA signed 2025-12-31 per developer milestone list

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

WATER AND COOLING

Lacy Lakeview Data District (L2D2): water and cooling

announced

Key data: Water demand: Roughly 2 million gallons per day at full build-out per local reporting; source not yet identified | Cooling: Chilled-water with free-cooling; design PUE 1.25; Tier III+ target

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

PERMITS AND JURISDICTION

Lacy Lakeview Data District (L2D2): permits and jurisdiction

announced

Key data: Jurisdictions: State of Texas | McLennan County | City of Lacy Lakeview | City of Waco ETJ | TCEQ (air permits) | ERCOT

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

CIVIC AND COMMUNITY

Lacy Lakeview Data District (L2D2): civic and community

announced

Waco council approved only a nonbinding MOU on a 6-1 vote amid resident concerns

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

announced

Annexation dispute: Lacy Lakeview is annexing land inside Waco's ETJ

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

ENVIRONMENT AND SITE

Lacy Lakeview Data District (L2D2): environment and site

announced

TCEQ air permits required for the planned 1.2 GW gas plant

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

announced

Water sourcing unresolved at ~2 MGD projected demand

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

announced

Key data: Surrounding infrastructure: Farmland west of Elm Mott, north of Waco

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

announced

Key data: Surrounding infrastructure: Requires a new 19-20 mile gas lateral

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

TIMELINE

Lacy Lakeview Data District (L2D2): timeline

announced

MOU signed between the city and developer

Claim classification: Not yet assigned

Status date: 2025-06

Open source 1 →

announced

Waco City Council approves nonbinding MOU 6-1

Claim classification: Not yet assigned

Status date: 2025

Open source 1 →

announced

Texas Tribune reports $10B project negotiations

Claim classification: Not yet assigned

Status date: 2025-11-24

Open source 1 →

announced

KWBU details water, power and political challenges

Claim classification: Not yet assigned

Status date: 2025-12-15

Open source 1 →

announced

Public-private partnership with Infrakey DC Parks LLC announced for a 925 MW district

Claim classification: Not yet assigned

Status date: 2026-01-15

Open source 1 →

announced

Developer milestone: 'Construction Permission from Brazos'

Claim classification: Not yet assigned

Status date: 2026-02-28

Open source 1 →

announced

Developer milestone: planned construction start

Claim classification: Not yet assigned

Status date: 2026-08-05

Open source 1 →

announced

Developer milestone: site energizing

Claim classification: Not yet assigned

Status date: 2027-10-29

Open source 1 →

CAPACITY GROSS POWER

Lacy Lakeview Data District (L2D2): capacity gross power

announced

The city announced a 925 MW data center district through a public-private partnership with Infrakey DC Parks LLC.

Key data: 925 MW announced district

Claim classification: REPORTED_FACT · Verification: VERIFIED_SINGLE_SOURCE · Retrieved: 2026-09-05

Status date: 2026-01-15

Open source 1 →

ONSITE GENERATION

Lacy Lakeview Data District (L2D2): onsite generation

announced

The $10 billion project on 520 acres west of Elm Mott includes a 1.2 GW gas-fired power plant, with up to 300 MW potentially sold to the grid.

Key data: 1.2 GW on-site gas plant; up to 300 MW exportable

Claim classification: REPORTED_FACT · Verification: VERIFIED_SINGLE_SOURCE · Retrieved: 2026-09-05

Status date: 2025-12-15

Open source 1 →

INTERCONNECTION

Lacy Lakeview Data District (L2D2): interconnection

announced

Infrakey's project page lists a direct ERCOT interconnection, an on-site substation, a 2024-10-01 interconnection request, a PCPA signed 2025-12-31, and site energizing planned for 2027-10-29.

Key data: Interconnection request 2024-10-01; energizing 2027-10-29

Claim classification: REPORTED_FACT · Verification: DEVELOPER_SELF_REPORTED · Retrieved: 2026-09-05

Status date: 2027-10-29

Limitation: Milestones are self-published by the developer and were not corroborated in ERCOT filings.

Open source 1 →

WATER DEMAND

Lacy Lakeview Data District (L2D2): water demand

announced

Local reporting flagged unresolved water sourcing for a project projected to need roughly 1 GW of power and a 19-20 mile gas lateral from the Hillsboro area.

Key data: ~1 GW demand; 19-20 mile gas line needed

Claim classification: REPORTED_FACT · Verification: VERIFIED_SINGLE_SOURCE · Retrieved: 2026-09-05

Status date: 2025-12-15

Open source 1 →

COMMUNITY RESPONSE

Lacy Lakeview Data District (L2D2): community response

announced

The Waco City Council approved only a nonbinding MOU on a 6-1 vote, and the unincorporated site sits inside Waco's extraterritorial jurisdiction.

Key data: 6-1 nonbinding MOU vote

Claim classification: REPORTED_FACT · Verification: VERIFIED_SINGLE_SOURCE · Retrieved: 2026-09-05

Status date: 2025-12-15

Open source 1 →

COOLING TECHNOLOGY

Lacy Lakeview Data District (L2D2): cooling technology

announced

The developer specifies chilled-water with free cooling, N+1 generators, a design PUE of 1.25 and Tier III+ targets, with Phase 1 at 163 MW.

Key data: PUE 1.25; Phase 1 163 MW; Tier III+

Claim classification: REPORTED_FACT · Verification: DEVELOPER_SELF_REPORTED · Retrieved: 2026-09-05

Status date: 2026-09-05

Open source 1 →