Developer: Lambda | County: Platte | Research region: Kansas City Northland | Tenants/customers: A single dedicated customer under a multi-year agreement (unnamed)
Claim classification: Not yet assigned
Status date: 2026-09-13
Open source 1 →
under construction
Missouri DED announced Lambda would establish an AI factory in an unoccupied 2009-built Kansas City Northland facility with 24 MW initially and more than 100 MW potential, more than 10,000 NVIDIA Blackwell Ultra GPUs, about $0.5 billion in the initial phase, a launch in early 2026 and a single dedicated customer under a multi-year agreement, using the Data Center Sales Tax Exemption.
Key data: 24 MW initial; >100 MW potential; >10,000 NVIDIA Blackwell Ultra GPUs
Claim classification: documented_fact · Verification: verified_by_primary_source · Retrieved: 2026-09-13
Status date: 2026
Limitation: The >100 MW figure is a stated potential, not a committed load.